Replacement of the horizontal boring machine and overhead crane at the Matsuura Plant
First written in FY2019. 4 of 5 entries say "Advanced", first in FY2021. Latest entry: FY2024.
No other company in this theme has enough history to compare yet.
- FY2024AdvancedAnnual report
「During the consolidated fiscal year, the Group made total capital investments of ¥930 million on a completed basis. In the machinery-related business, the Group made capital investments of ¥688 million, mainly for the renewal of the 60T jib crane at the Matsuura Plant.」
Capital investment, including replacement of the 60T jib crane at the Matsuura Plant, progressed throughout the fiscal year, with ¥688 million invested in the machinery-related business. - FY2024-Q1AdvancedAnnual report
「Due mainly to the recognition of a ¥130 million loss on disposal of property, plant and equipment related to crane replacement and other activities in the machinery-related business as an extraordinary loss, the quarterly net loss attributable to owners of the parent was ¥2 million.」
A ¥130 million loss on disposal of property, plant and equipment related to crane replacement at the Matsuura Plant and elsewhere was recognized, indicating that the equipment replacement had reached the disposal stage for accounting purposes. - FY2023AdvancedAnnual report
「Company Matsuura Plant Matsuura City, Nagasaki Prefecture Machinery-related business 60T jib crane 475,649 236,160 Internal funds May 2022 May 2023」
Replacement of the 60T jib crane at the Matsuura Plant progressed, with a total cost of ¥475.649 million and ¥236.160 million already paid. - FY2021AdvancedAnnual report
「Company Matsuura Plant Matsuura City, Nagasaki Prefecture Machinery-related business Horizontal boring machine 182,590 58,900 Internal funds February 2020 June 2021 Company Matsuura Plant Matsuura City, Nagasaki Prefecture Machinery-related business 60T jib crane 450,000 - Internal funds July 2021 May 2023」
For the horizontal boring machine, a paid amount of ¥58.9 million and scheduled completion in June 2021 were disclosed. The replacement plan for the 60T jib crane was also specified, with work scheduled to begin in July 2021 and be completed in May 2023. - FY2019First statedAnnual report
「Company Matsuura Plant Machinery-related business Horizontal boring machine 230,000 - Internal funds August 2019 March 2021 Company Matsuura Plant Machinery-related business Overhead crane 75,000 - Internal funds June 2019 January 2020」
New replacement plans were disclosed for a horizontal boring machine costing ¥230 million and an overhead crane costing ¥75 million at the Matsuura Plant.