Delay in Investment Plans for Distributed Power Sources
First written in FY2020-Q1. 3 of 6 entries say "Restated". Latest entry: FY2024-Q3.
0 other companies' latest entry also says "Restated".
- FY2024-Q3RestatedAnnual report
「In addition, demand for distributed power generation in Japan and overseas and demand for energy infrastructure development in emerging economies remain robust, while replacement demand for ageing waste incineration facilities in Japan also continues.」
The view that replacement demand for distributed power generation, energy infrastructure and waste incineration facilities remains robust continues to be stated. - FY2023-Q1RestatedAnnual report
「Demand for distributed power generation in Japan and overseas and demand for energy infrastructure development in emerging economies remain robust, while replacement demand for ageing waste incineration facilities in Japan also continues.」
The view that demand for distributed power generation, energy infrastructure and waste incineration facilities remains robust continues to be stated. - FY2022-Q3RestatedAnnual report
「Demand for distributed power generation in Japan and overseas and demand for energy infrastructure development in emerging economies remain robust, while replacement demand for ageing waste incineration facilities in Japan also continues.」
The view that demand for distributed power generation and energy infrastructure remains robust continues to be stated. - FY2022-Q1MitigatedAnnual report
「Demand for distributed power generation in Japan and overseas and demand for energy infrastructure development in emerging economies remain robust, while replacement demand for ageing waste incineration facilities in Japan also continues.」
In contrast to the previous concerns, centred on delays in customers' capital investment decisions for distributed power generation, it was stated that demand in Japan and overseas remains robust. - FY2021-Q1WorsenedAnnual report
「Meanwhile, uncertainty continues as customers reconsider their short-term capital investment decisions due to stagnant economic activity caused by the spread of COVID-19 and unstable resource prices.」
An additional risk was described in the energy and environmental plant sector, including distributed power generation, that customers may reconsider short-term capital investment decisions due to the spread of COVID-19 and other factors. - FY2020-Q1First statedAnnual report
「Although potential demand for distributed power generation is substantial, investment plans have been somewhat delayed in anticipation of electricity market liberalisation.」
A new description was added of the business environment in which investment plans for distributed power generation are being delayed against the backdrop of electricity market liberalisation, despite substantial potential demand.