Expansion of NT die-cutter production capacity at the Kiyama Plant
First written in FY2017. 2 of 3 entries say "Advanced", first in FY2018. Latest entry: FY2020.
No other company in this theme has enough history to compare yet.
- FY2020AdvancedAnnual report
「Capital investment for the consolidated fiscal year totaled ¥1,174 million, consisting mainly of additions to production facilities to increase NT Die Cutter production and new capital investment by a Brazilian subsidiary.」
The company made capital investments totaling ¥1,174 million, including equipment to increase NT Die Cutter production and equipment at its Brazilian subsidiary. - FY2018AdvancedAnnual report
「In particular, to expand production capacity for the important NT Die Cutter product, the company expanded the Kiyama Plant in March 2018 and began production in May.」
The expansion of the NT Die Cutter building at the Kiyama Plant was completed in March 2018, and production began in May. - FY2017First statedAnnual report
「To accommodate expected future demand growth and expand production capacity, the company decided to construct an addition to the building at its Kiyama Plant, scheduled for completion in March 2018.」「Kiyama Plant … NT Die Cutter building … total ¥1,000 million … August 2017 … March 2018 … production capacity increase of 100%」」
The company plans to expand the NT Die Cutter building at the Kiyama Plant at a total cost of ¥1 billion, with completion scheduled for March 2018 and production capacity planned to increase by 100%.