Nkk Switches (6943) · InitiativeHigher investment and delayed completion
Construction of a New Factory for NKK Switches Pionics
First written in FY2024. 1 of 3 entries say "Advanced", first in FY2025. Latest entry: FY2026.
3entries
3years
0from disclosures
How it moved
Same theme, other companies
Strengthening the domestic production system through construction of a new Pionix plantA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2026Higher investment and delayed completionAnnual report
「NKKスイッチズ パイオニクス Co., Ltd. (Totsuka-ku, Yokohama, Kanagawa Prefecture) Japan Switch production equipment (new plant) 2,427 1,264 Internal funds and borrowings 2023.6 2027.3」
Due to soaring material prices, the planned total investment for the new plant increased from ¥1.55 billion to ¥2.427 billion, and the amount already paid reached ¥1.264 billion. The scheduled completion date changed to March 2027. - FY2025AdvancedAnnual report
「NKKスイッチズ パイオニクス Co., Ltd. (Totsuka-ku, Yokohama, Kanagawa Prefecture) Japan Switch production equipment (new plant) 1,550 734 Internal funds and other sources 2023.6 2026.5」
For the NKKスイッチズ パイオニクス new plant project, the amount already paid increased from the ¥674 million previously reported to ¥734 million. The total investment remains ¥1.55 billion, with completion scheduled for May 2026. - FY2024First statedAnnual report
「NKKスイッチズ パイオニクス Co., Ltd. Switch production equipment (new plant) 1,550 674 Internal funds and other sources 2023.6 2026.5」
As part of efforts to strengthen domestic production, the company is proceeding with a new plant project with a total investment of ¥1.55 billion and ¥674 million already paid, with completion scheduled for May 2026.