Strengthening the Global Production System by Expanding Mass-Production Sites Outside China
First written in FY2023. 3 of 4 entries say "Advanced", first in FY2024. Latest entry: FY2026.
108 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「Specifically, we will bring production at the second Kulim plant in northern Malaysia, scheduled to begin operations in 2026, onto a stable footing to meet customers' procurement needs, while proceeding with plant construction in Beijing, Hefei, Shaoxing and Wuhan, China.」
The company identified the start of operations at the second Malaysia-Kulim plant in 2026 as a mass-production site outside China, while also presenting plans to proceed with plant construction in Beijing, Hefei, Shaoxing and Wuhan, China. - FY2026-H1AdvancedAnnual report
「In our Group's semiconductor and other equipment-related businesses, we worked to meet procurement needs outside China among European and US customers, primarily through Malaysia, while also seeking to capture demand within China. As a result, sales of vacuum components for manufacturing equipment, contract metal processing and ceramics products increased.」
Regarding the development of mass-production and procurement sites outside China, the company captured European and US customers' demand for procurement outside China, centered on Malaysia, leading to increased sales of vacuum components, contract metal processing and ceramics products. - FY2024AdvancedAnnual report
「Specifically, we will accelerate efforts to capture customer demand in Southeast Asia by bringing production at the semiconductor equipment-related plant in northern Malaysia, in Kulim, which began operations in January 2024, fully on track. We also aim to establish the power semiconductor insulating substrate plant in southern Malaysia, in Johor Bahru, at an early date.」
Regarding the development of production sites outside China, the Kulim plant in northern Malaysia began operations in January 2024. The company has also reached the stage of proceeding with the establishment of a power semiconductor substrate plant in Johor Bahru and the establishment and expansion of sites in Kumamoto and Ishikawa, Japan. - FY2023First statedAnnual report
「To support business growth while responding to changes in the operating environment, we will strengthen our global production system by expanding mass-production sites to regions outside China. In Southeast Asia, where leading European and US semiconductor manufacturers are making significant inroads, we are proceeding with the construction of a plant in Malaysia, while also expanding the Ishikawa Plant and establishing a new Kumamoto Plant to increase our share of demand for semiconductor manufacturing equipment in Japan.」
With a focus on diversifying away from concentration in China, the company identified the development of mass-production sites combining the Malaysia plant, expansion of the Ishikawa Plant and establishment of a new Kumamoto Plant as new challenges and initiatives. The capital investment plan for the following year is ¥96.9 billion.