Approval of disclosure concerning completion of grid interconnection for a grid-scale battery storage facility to be acquired by our subsidiary

Grid interconnection for the grid-scale battery storage facility in Setaka Town, Miyama City, Fukuoka Prefecture, which is scheduled to be acquired by a subsidiary, was completed on 1 July 2026. The interconnection was completed ahead of the original schedule of sometime in July, and handover is scheduled for mid-August 2026.

Worth reading
62In focus
Scored from 4 of 5 sections
Direction
Improvement
Direction inferred from the company’s description.
Scale
6.84
¥ hundred million
Wording
Definitive
How definitive the wording is.

This transaction

Acquisition of a grid-scale battery storage facility
TimelineThe spacing between the points is proportional to the actual number of days.
Target company
Location Setaka-cho, Miyama, Fukuoka Prefecture
Consideration and expenses
Acquisition priceApproximately ¥684 million
Type of ConsiderationCash
Funding arrangementsInternal funds
Impact on Business Performance

The impact on the Company's consolidated results for the fiscal year ending October 2026 has already been reflected in the forecasts.

Procedures and assumptions
Conditions Precedent to ExecutionVarious procedures and reviews required to enter the supply-demand adjustment market
Management structure after acquisitionFollowing handover, the Company will proceed with the procedures and reviews required to enter the balancing market and aims to commence operations at an early date
This transaction
ItemDetails
Transaction nameAcquisition of a grid-scale battery storage facility
Location of the Subject CompanySetaka-cho, Miyama, Fukuoka Prefecture
Acquisition priceApproximately ¥684 million
Type of ConsiderationCash
Funding arrangementsInternal funds
Impact on Business PerformanceThe impact on the Company's consolidated results for the fiscal year ending October 2026 has already been reflected in the forecasts.
Date of board resolution25 May 2026
Contract Date25 May 2026
Execution Date / Effective DateMid-August 2026 (scheduled)
Conditions Precedent to ExecutionVarious procedures and reviews required to enter the supply-demand adjustment market
Management structure after acquisitionFollowing handover, the Company will proceed with the procedures and reviews required to enter the balancing market and aims to commence operations at an early date
Items this document does not state (21)
Counterparty nameName of the Subject CompanyBusiness Description of the Subject CompanyCapital Stock of the Subject CompanyDate of Establishment of the Subject CompanyNet Sales of the Subject CompanyOperating Profit of the Subject CompanyNet Income of the Subject CompanyNet Assets of the Subject CompanyExpenses other than the acquisition priceMerger ratio/share exchange ratioTender offer priceMinimum number of shares to be purchasedTender offer periodNumber of shares acquiredVoting rights ownership percentageGoodwill amountAmount of extraordinary income (loss)Valuation methodologyIndependent valuation institutionSpecial Committee

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The Company recognizes that developing grid-scale battery storage facilities to support a stable electricity supply is essential to the wider adoption of renewable energy, and is therefore proceeding with its entry into the grid-scale battery storage business. Following handover, the Company will proceed with the procedures and reviews required to enter the balancing market and aims to commence operations at an early date.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Approval of disclosure concerning completion of grid interconnection for a grid-scale battery storage facility to be acquired by our subsidiary | TAMAGAWA HOLDINGS CO.,LTD. (6838) timely disclosure | Komori