Kyosan Electric Manufacturing (6742) · InitiativeRestated

Restructuring the Head Office Plant as a Production Base

First written in FY2016. 4 of 10 entries say "Restated". Latest entry: FY2024.

10entries
9years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2016 – FY2018AdvancedFY2022-Q1 – FY20222016: 120162017: 020172018: 120182019: 120192020: 120202021: 420212022: 120222023: 020232024: 12024
Same theme, other companies
Reconstruction of the Head Office PlantA theme 6 companies write about · 0 as a headwind · 6 as a tailwind

0 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2024RestatedAnnual report

    「Capital expenditures for the fiscal year, including software, were ¥485 million for the Signal Systems business, ¥106 million for the Power Electronics business and ¥348 million company-wide, for a total of ¥941 million. Major expenditures included routine renewals, labor-saving and rationalization investments to address the current economic environment, and investments associated with rebuilding the production base at the head office factory.」

    The company continued capital investment, including rebuilding the production base at the head office factory and labor-saving and rationalization investments.
  2. FY2022AchievedAnnual report

    「Under these circumstances, the Group focused on an early recovery from the fire that occurred on 14 January 2021 and a recovery in business performance, and completed restoration work on the damaged buildings in September 2021,」

    Restoration work on the damaged buildings following the head office factory fire was completed in September 2021.
  3. FY2022-Q2AdvancedAnnual report

    「Under these circumstances, the Group focused on an early recovery from the fire that occurred on 14 January 2021 and a recovery in business performance, and completed restoration work on the damaged buildings in September this year.」

    Regarding recovery following the head office factory fire, restoration work on the damaged buildings was completed in September 2021.
  4. FY2022-Q1AdvancedAnnual report

    「As of the end of the first quarter, the order backlog was ¥103,054 million, up ¥13,760 million from the end of the previous consolidated fiscal year. Regarding production facilities, the company had secured operating space equivalent to the pre-fire level, including leased external space, by the end of the first quarter. In addition, full renovation of the factory building, which was the main damaged area, is expected to be completed by the end of the second quarter of the current consolidated fiscal year.」

    Regarding recovery following the head office factory fire, the company has secured operating space equivalent to the pre-fire level and expects to complete full renovation of the factory building by the end of the second quarter, indicating concrete progress. The order backlog has also increased to ¥103,054 million.
  5. FY2021RestatedAnnual report

    「The company has already resumed production using undamaged buildings on the head office factory site and other Group locations. It expects to complete repairs to the damaged buildings during the first half of the fiscal year ending March 2022 and restore its pre-fire production structure.」

    The company reiterated that production had resumed following the fire and that it expects to restore its pre-fire production structure during the first half of the fiscal year ending March 2022.
  6. FY2021-Q3AdvancedAnnual report

    「As of the filing date, the company had resumed operations using buildings on the head office factory site that escaped damage and other Group locations. Restoration to the operating level before the fire is expected during the first half of the fiscal year ending March 2022, when renovation work on the damaged buildings is scheduled to be completed.」

    Following the fire at the head office factory, the company resumed operations using undamaged buildings and Group locations, and expects to restore operations to pre-fire levels during the first half of the fiscal year ending March 2022.
  7. FY2020RestatedAnnual report

    「Capital expenditures for the fiscal year, including software, were ¥883 million for the Signal Systems business, ¥276 million for the Power Electronics business and ¥619 million company-wide, for a total of ¥1,779 million. Major expenditures included routine renewals, labor-saving and rationalization investments to address the current economic environment, and investments associated with rebuilding the production base at the head office factory.」

    The company continued capital investment, including rebuilding the production base at the head office factory and labor-saving and rationalization investments.
  8. FY2019AdvancedAnnual report

    「Capital expenditures for the fiscal year, including software, were ¥644 million for the Signal Systems business, ¥861 million for the Power Electronics business and ¥513 million company-wide, for a total of ¥2,019 million. Major expenditures included routine renewals, labor-saving and rationalization investments to address the current economic environment, and investments associated with rebuilding the production base at the head office factory.」

    Capital expenditures, including rebuilding the production base at the head office factory and labor-saving and rationalization investments, totaled ¥2,019 million, up from ¥1,773 million in the previous fiscal year.
  9. FY2018RestatedAnnual report

    「Capital expenditures for the fiscal year, including software, were ¥919 million for the Signal Systems business, ¥480 million for the Electrical Equipment business and ¥374 million company-wide, for a total of ¥1,773 million. Major expenditures included routine renewals, labor-saving and rationalization investments to address the current economic environment, and investments associated with rebuilding the production base at the head office factory.」

    The company continued capital investment, including rebuilding the production base at the head office factory and labor-saving and rationalization investments.
  10. FY2016First statedAnnual report

    「Capital expenditures for the fiscal year, including software, were ¥1,080 million for the Signal Systems business, ¥210 million for the Electrical Equipment business and ¥749 million company-wide, for a total of ¥2,040 million. Major expenditures included routine renewals, labor-saving and rationalization investments to address the current economic environment, and investments associated with rebuilding the production base at the head office factory.」

    The company made total capital expenditures of ¥2,040 million, including investments in rebuilding the production base and labor-saving and rationalization measures.
Moved together

"Business structure reform integrating technology, quality, costs and sales" moved the same way as this thread, in the same document, in 4 of its 10 moves.

433333★123456
  1. ★This thread
  2. 1Business structure reform integrating technology, quality, costs and sales4×
  3. 2Growing Demand for Power Supply Equipment for Semiconductor and LCD Manufacturing Equipment3×
  4. 3Managing Funding Efficiency and Liquidity through CMS and Committed Credit Lines3×
  5. 4Deterioration in Operating Cash Flow Due to Increased Inventories, etc., and Increase in Borrowings3×
  6. 5Demand Fluctuation and Technological Innovation Risks in the Semiconductor and FPD Industries3×
  7. 6Strengthening the Technology Base Through Product Development and Improvement3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Kyosan Electric Manufacturing yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Restructuring the Head Office Plant as a Production Base | Kyosan Electric Manufacturing Co.,Ltd. (6742) | Komori