Insufficient Conversion of Orders into Sales and Earnings Due to Production Capacity Constraints
First written in FY2026. 1 of 2 entries say "Materialised", first in 2026-10-04. Latest entry: 2026-10-04.
Ulvac moved to the "Worse" side of this theme in 2026.
2 other companies' latest entry also says "Materialised".
- 2026-10-04Materialisednewswitch.jp
「In addition to the increased difficulty of procuring materials across the company, the Chigasaki Plant has only recently established its production system and is still in a transition period, resulting in delays of approximately 2–3 months compared with the usual lead time of around 1 year.」
It was reported that delivery of ordered vacuum furnaces has been delayed by approximately 2–3 months while the Chigasaki Plant's production system is being established. - FY2026First statedAnnual report
「However, due to the emergence of risks related to component supplies and production capacity constraints, the Company has not been able to convert the orders secured fully into revenue and profit and recognizes improving profitability as a key management issue.」
In FY2026, despite record-high orders received, the company was unable to convert orders sufficiently into revenue and profit due to the emergence of materials supply risks and production capacity constraints.