Komori
Saxa (6675) · RiskMaterialised

Impairment losses associated with a review of the use of owned real estate

First written in FY2023-Q3. 2 of 4 entries say "Materialised", first in FY2025. Latest entry: FY2026.

4entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2023-Q3OtherFY2026-H12023: 120232024: 020242025: 220252026: 12026
Same theme, other companies
Impairment of Fixed Assets Arising from Changes in the Use of Operating LocationsA theme 3 companies write about · 3 as a headwind · 0 as a tailwind

Saxa moved to the "Worse" side of this theme in 2025.

1 other company's latest entry also says "Materialised".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026MaterialisedAnnual report

    「The company decided in June 2025 to relocate its head office from its owned office property and reduced the carrying amount of assets with no planned future use to their recoverable amount. The company also decided in March 2026 to relocate its owned office property in Yokohama, Kanagawa Prefecture, and office properties owned by its subsidiaries, and reduced the carrying amount of assets with no planned future use to their recoverable amount.」

    Impairment losses associated with the review of property use and relocation of sites were actually recognized at ¥172 million for Yokohama, Tokyo and Sapporo in the current fiscal year, compared with ¥91 million in the previous fiscal year.
  2. FY2026-H1Impairment loss recorded for the interim periodAnnual report

    「Impairment losses 91 30」

    Impairment losses decreased from ¥91 million in the interim period of the previous year to ¥30 million in the current interim consolidated accounting period.
  3. FY2025MaterialisedAnnual report

    「The increase resulting from this change in estimate was recognized as an asset retirement obligation, while the building recognized at the same time was recognized as an impairment loss.」

    For the real estate owned in Sagamihara, the company progressed from the estimate associated with the review of its use and actually recognized an impairment loss of ¥91 million on the building.
  4. FY2023-Q3First statedAnnual report

    「As a result, the company expects to recognize impairment losses of up to ¥1,053 million.」

    In connection with reviewing the use of owned real estate in Sagamihara as rental property, the company disclosed that it expects to recognize impairment losses of up to ¥1,053 million in the fourth quarter of the fiscal year ending March 2023. This was still an estimate and had not actually been recognized as of the end of the third quarter.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Saxa yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.