This transaction
Transfer of fixed assets (plant) and construction of a new plantA plant primarily engaged in the manufacture of injection-molded products
The impact of the transfer of fixed assets has not been included in the consolidated earnings forecast for the fiscal year ending March 2027. The company plans to disclose the transfer price and its impact on the financial results once they have been determined. The impact of constructing the new plant has already been included in the consolidated earnings forecast.
| Item | Details |
|---|---|
| Transaction name | Transfer of fixed assets (plant) and construction of a new plant |
| Business Description of the Subject Company | A plant primarily engaged in the manufacture of injection-molded products |
| Location of the Subject Company | Yonezawa, Yamagata Prefecture |
| Acquisition price | Undetermined (transfer price) |
| Amount of extraordinary income (loss) | Gain or loss on transfer, etc.: Undetermined |
| Impact on Business Performance | The impact of the transfer of fixed assets has not been included in the consolidated earnings forecast for the fiscal year ending March 2027. The company plans to disclose the transfer price and its impact on the financial results once they have been determined. The impact of constructing the new plant has already been included in the consolidated earnings forecast. |
| Date of board resolution | 5 June 2026 |
| Contract Date | January 2027 (予定) |
| Execution Date / Effective Date | Date of transfer of ownership of the facility: Not disclosed / Start of operations at the new plant: March 2028 (scheduled) |
| Management structure after acquisition | The production functions of the facility will be transferred to the new plant. From the date of settlement of the remaining transfer price for the fixed assets (the date of transfer of ownership) until completion of the new plant, the company plans to enter into a fixed-term building lease agreement under which the seller will be the lessee and the buyer will be the lessor. |
Items this document does not state (22)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The reasons include the aging of the existing plant, potential improvements in productivity and efficiency through the consolidation of dispersed sites, strengthening of business continuity planning, consolidation of plant functions, reinforcement of the supply chain, and expanded use of environmentally friendly plastics. In light of rising raw material prices and construction costs, the company also significantly reduced the scale and budget of its Yonezawa Advanced Factory initiative.