How definitive the wording is.Decision and Details
Progress on the design of the World Innovation Center (WIC)
Decision1 June 2026 (disclosure date)
Period CoveredThrough the scheduled completion (scheduled for 2031)
ImplementationThe design has changed from scheme design to preliminary design.
Going forwardThe basic framework of the building plans and other details is expected to be finalized by around December 2026. The details will be disclosed promptly once they have been organized. Completion is scheduled for 2031.
Quantity / scaleSite area: 21,991 m²; gross floor area: 454,500 m²; 4 basement levels and 54 above-ground floors; maximum height: 248 m; 2 research and development buildings approximately 250 m in height and 1 ancillary residential building approximately 150 m in height
Reason
The building plans are being further detailed as the preliminary design progresses.
Impact on Business Performance
This matter will have no impact on the Company's performance.
| Item | Details |
|---|---|
| Matter Covered | Progress on the design of the World Innovation Center (WIC) |
| Decision Date | 1 June 2026 (disclosure date) |
| Implementation Date | The design has changed from scheme design to preliminary design. |
| Period Covered | Through the scheduled completion (scheduled for 2031) |
| Quantity / scale | Site area: 21,991 m²; gross floor area: 454,500 m²; 4 basement levels and 54 above-ground floors; maximum height: 248 m; 2 research and development buildings approximately 250 m in height and 1 ancillary residential building approximately 150 m in height |
| Impact on Business Performance | This matter will have no impact on the Company's performance. |
| Reason | The building plans are being further detailed as the preliminary design progresses. |
| Future plans | The basic framework of the building plans and other details is expected to be finalized by around December 2026. The details will be disclosed promptly once they have been organized. Completion is scheduled for 2031. |
Items this document does not state (4)
Decision-Making BodyAmountGoverning RuleRelated previous disclosures
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The building plans are being further detailed as the preliminary design progresses.
How to read this page
This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.