Yushin Company (6482) · InitiativeCited as achieved
Head Office System Go-Live
First written in FY2017-Q2. 1 of 3 entries say "Achieved", first in FY2017-Q3. Latest entry: FY2017.
3entries
2years
0from disclosures
How it moved
Same theme, other companies
Head office system go-live planA theme 1 companies write about · 0 as a headwind · 0 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2017Cited as achievedAnnual report
「Costs associated with launching the internal core system, which began operations last November」
Cited the head office system as a completed project that had already begun operations in November 2016. - FY2017-Q3AchievedAnnual report
「The head office system, which was under development at the end of the 43rd consolidated fiscal year, was completed in November 2016, and the new head office plant was completed in December 2016.」
Reported that the head office system was completed in November 2016, reaching the completion stage from its previously scheduled operating phase. - FY2017-Q2First statedAnnual report
「The scheduled start of operations for the head office system changed from July-September 2016 to November 2016.」
Reported that the scheduled start of operations for the head office system changed from July-September 2016 to November 2016.