Consideration of measures to address aging at the head office plant and BCP preparations
First written in FY2020. 2 of 4 entries say "Advanced", first in FY2025-H1. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AdvancedAnnual report
「Our group acquired industrial land on Port Island to prepare for emergencies such as natural disasters, ensure business continuity and strengthen the resilience of the supply chain for products and services, with the aim of implementing BCP (business continuity plan) measures, enhancing factory functions and strengthening research and development functions.」
The acquisition of land on Port Island was completed in June 2025, moving development of a site to strengthen BCP, factory functions and research and development functions from the decision stage to the acquisition-completed stage. The specific construction timetable has not been determined. - FY2025-H1AdvancedAnnual report
「As disclosed in the press release dated 7 March 2025, we decided to acquire land on Port Island from Kobe City for the purposes of BCP measures, enhancing factory functions and strengthening research and development functions.」
To address the aging of the head office factory and the concentration of production, the company decided to acquire land on Port Island in Kobe City to strengthen BCP, factory functions and research and development functions. The company progressed from the previous consideration stage to a specific decision to acquire a site. - FY2021RestatedAnnual report
「We will diligently consider seismic retrofits to the factory buildings and relocation to a suitable site, while steadily advancing BCP measures for emergencies.」
The company continues to consider seismic retrofits and relocation for the aging head office factory, as well as BCP measures. - FY2020First statedAnnual report
「We are therefore currently conducting simulations of various measures, and recognize the need to reach a final conclusion within several years and begin implementing some form of measures.」
The company first specified a policy of conducting simulations of multiple measures for the aging head office factory, reaching a final conclusion within several years and aiming to begin implementation.