Trinity Industrial (6382) · RiskUpdated revenue from construction contracts

Revenue-recognition risk arising from changes in estimated construction costs

First written in FY2021. 12 of 14 entries say "Restated". Latest entry: FY2026.

14entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2021 – FY20262021: 320212022: 420222023: 320232024: 320242025: 020252026: 12026
Same theme, other companies
Uncertainty in Cost and Progress Estimates for Construction Revenue RecognitionA theme 97 companies write about · 96 as a headwind · 1 as a tailwind

The whole theme swung hardest in 2024: 10 of 66 companies on the "Worse" side.

23 other companies' latest entry also says "Other".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 97 companies compared. The sentences above are computed from all 97.
Full recordFilings, disclosures and news, newest first
  1. FY2026Updated revenue from construction contractsAnnual report

    「Revenue from construction contracts relating to performance obligations satisfied over time was 13,342,512 thousand yen. In the future, changes in the assumptions underlying the initial estimates may arise from changes in the conditions underlying the estimate of total construction costs, such as design changes or natural disasters, and may have a material impact on the amounts recognized in the consolidated financial statements for the following consolidated fiscal year.」

    The risk associated with revenue recognition for construction contracts continues, and revenue from construction contracts relating to performance obligations satisfied over time was ¥13,342,512,000.
  2. FY2025-H1RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the assumptions concerning revenue recognition for construction contracts and estimated construction costs.
  3. FY2024RestatedAnnual report

    「Revenue from construction contracts relating to performance obligations satisfied over time was 12,411,644 thousand yen. In the future, changes in the assumptions underlying the initial estimates may arise from changes in the conditions underlying the estimate of total construction costs, such as design changes or natural disasters, and may have a material impact on the amounts recognized in the consolidated financial statements for the following consolidated fiscal year.」

    Revenue recognized for construction contracts was ¥12,411,644,000, and the risk of changes in estimated construction costs resulting from design changes, natural disasters and other factors continues.
  4. FY2024-Q3RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the assumptions concerning revenue recognition based on construction progress and estimated construction costs.
  5. FY2024-Q2RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the assumptions concerning revenue recognition based on construction progress and estimated construction costs.
  6. FY2024-Q1RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the assumptions concerning revenue recognition based on construction progress and estimated construction costs.
  7. FY2023RestatedAnnual report

    「Revenue from construction contracts relating to performance obligations satisfied over time was 7,835,067 thousand yen. In the future, changes in the assumptions underlying the initial estimates may arise from changes in the conditions underlying the estimate of total construction costs, such as design changes or natural disasters, and may have a material impact on the amounts recognized in the consolidated financial statements for the following consolidated fiscal year.」

    The risk associated with revenue recognition for construction contracts continues, and revenue from construction contracts relating to performance obligations satisfied over time was ¥7,835,067,000 for the current fiscal year.
  8. FY2023-Q2RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the accounting estimates and assumptions concerning revenue recognition based on construction progress and estimated construction costs.
  9. FY2023-Q1RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the accounting estimates and assumptions concerning revenue recognition based on construction progress and estimated construction costs.
  10. FY2022RestatedAnnual report

    「Revenue from construction contracts relating to performance obligations satisfied over time was 13,987,869 thousand yen. In the future, changes in the assumptions underlying the initial estimates may arise from changes in the conditions underlying the estimate of total construction costs, such as design changes or natural disasters, and may have a material impact on the amounts recognized in the consolidated financial statements for the following consolidated fiscal year.」

    Revenue recognized based on construction progress was 13,987,869 thousand yen, and the risk of changes in estimated construction costs resulting from design changes, natural disasters and other factors continues.
  11. FY2022-Q3RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the accounting estimates and assumptions concerning revenue recognition under the percentage-of-completion method and estimated construction costs.
  12. FY2022-Q2RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the accounting estimates and assumptions concerning revenue recognition under the percentage-of-completion method and estimated construction costs.
  13. FY2022-Q1RestatedAnnual report

    「There have been no material changes to the accounting estimates and the assumptions used in those estimates described under “Management's Analysis of Financial Position, Operating Results and Cash Flows” in the securities report for the previous fiscal year.」

    It is stated that there have been no material changes to the accounting estimates and assumptions concerning revenue recognition under the percentage-of-completion method and estimated construction costs.
  14. FY2021First statedAnnual report

    「Revenue of 15,981,428 thousand yen was recognized under the percentage-of-completion method. In the future, changes in the assumptions underlying the initial estimates may arise from changes in the conditions underlying the estimate of total construction costs, such as design changes requested by customers or natural disasters, and may have a material impact on the amounts recognized in the consolidated financial statements for the following consolidated fiscal year.」

    Revenue of 15,981,428 thousand yen was recognized under the percentage-of-completion method, and the Company newly disclosed that changes in estimated construction costs resulting from design changes, natural disasters and other factors could have a material impact on future financial statements.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Trinity Industrial's next results are scheduled for 2026-10-28. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.