Chubu Branch Relocation
First written in FY2022. 3 of 6 entries say "Restated". Latest entry: FY2024-Q3.
No other company in this theme has enough history to compare yet.
- FY2024-Q3RestatedAnnual report
「The planned relocation of the company's Chubu Branch office, classified as a major facility project at the end of the previous consolidated fiscal year, was completed as planned during the first quarter of the current consolidated fiscal year.」
The company continued to disclose in its third-quarter report that the Chubu Branch office relocation was completed as planned in the first quarter. - FY2024-Q1AchievedAnnual report
「The planned relocation of the company's Chubu Branch office, classified as a major facility project at the end of the previous consolidated fiscal year, was completed as planned during the cumulative first quarter of the current consolidated fiscal year.」
The planned relocation of the Chubu Branch office was completed as scheduled. - FY2023RestatedAnnual report
「Company; Chubu Branch; Aichi; Nagoya; Japan; office relocation; 593; 464; internal funds; July 2022; April 2023」
For the Chubu Branch relocation, the company continues to disclose the plan of a total investment of ¥593 million, ¥464 million already paid and scheduled completion in April 2023. - FY2023-Q3RestatedAnnual report
「Planned investment amount; total 593; already paid 464; internal funds; commencement July 2022; completion April 2023」
For the Chubu Branch relocation, the company continues to disclose the plan, following the previous change, of a total investment of ¥593 million, ¥464 million already paid and scheduled completion in April 2023. - FY2023-Q2SoftenedAnnual report
「Planned investment amount; total 593; already paid 332; internal funds; commencement July 2022; completion April 2023」
The scheduled completion date for the Chubu Branch relocation changed from February 2023 to April 2023, a 2-month delay. - FY2022First statedAnnual report
「Chubu Branch; Nagoya, Aichi, Japan; office relocation; 593; 40; internal funds; July 2022; February 2023」
For the relocation of the Chubu Branch office, the company disclosed a total planned investment of ¥593 million, ¥40 million already paid, financing from internal funds, commencement in July 2022 and scheduled completion in February 2023.