Revised forecast
Fiscal year ending March 2027 · Second quarter (interim period) and full yearPrevious forecast published Interim period 31 July 2026 / Full year 15 May 2026The bar length represents the relative magnitude of change, based on the item that changed the most in this document. The percentage change shown by the dotted line is calculated from the two reported figures because the company did not provide the rate.
Revenue for the interim period fell below the initial forecast due to delays in the progress of certain large construction projects and other factors. The forecast was revised because the Company expects to recover from delays in first-half construction projects, steady progress on construction projects already received and those received during the current fiscal year that will contribute to revenue in the second half, and improvements in construction costs.
| Item | Details |
|---|---|
| Net Sales | Interim period 43,000 / Full year 80,000 → Interim period Actual results 38021 / Full year 83,500(Interim period -11.6 / Full year 4.4) |
| Operating profit | Interim period 4,200 / Full year 8,800 → Interim period Actual results 3917 / Full year 9,500(Interim period -6.7 / Full year 8) |
| Ordinary income | Interim period 4,300 / Full year 8,900 → Interim period Actual results 3910 / Full year 9,300(Interim period -9.1 / Full year 4.5) |
| Profit attributable to owners of the parent | Interim period 3,690 / Full year 6,850 → Interim period Actual results 3163 / Full year 7,450(Interim period -14.3 / Full year 8.8) |
| Net income per share | Interim period 161.98 / Full year 300.69 → Interim period Actual results 138.85 / Full year 327.03 |
| Fiscal Period Covered | Fiscal year ending March 2027 |
| Period Covered | Second quarter (interim period) and full year |
| Publication date of previous forecast | Interim period 31 July 2026 / Full year 15 May 2026 |
| Previous-period results | Interim period Net Sales 36,123 / Operating profit 3,681 / Ordinary income 3,864 / Interim net income attributable to owners of the parent 2,679 / Interim net income per share 117.64 / Fiscal Period Covered Interim period of the fiscal year ending March 2026 / Full year Net Sales 84,240 / Operating profit 9,181 / Ordinary income 9,462 / Profit attributable to owners of the parent 7,546 / Net income per share 331.34 / Fiscal Period Covered Fiscal year ending March 2026 |
| Reason for the revision | Revenue for the interim period fell below the initial forecast due to delays in the progress of certain large construction projects and other factors. The forecast was revised because the Company expects to recover from delays in first-half construction projects, steady progress on construction projects already received and those received during the current fiscal year that will contribute to revenue in the second half, and improvements in construction costs. |
| Consolidated / non-consolidated | Consolidated |
Items this document does not state (2)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.Revenue for the interim period fell below the initial forecast due to delays in the progress of certain large construction projects and other factors. For the full year, the Company has revised its earnings forecast upward, expecting to recover from delays in first-half construction projects, steady progress on construction projects already received and those received during the current fiscal year, and improvements in construction costs.