First quarter1 April 2026 to 30 June 2026ConsolidatedJapanese GAAPThe width of the band at each stage is based on revenue. The narrower it becomes toward the bottom, the smaller the proportion of revenue that remains as profit. The dotted outline is the full-year forecast and the band inside it is the result for this period. The progress rate is the result divided by the forecast.
塗りつぶした部分が自己資本比率です。総資産のうち、返済のいらない自前の資金がどれだけかを表します。The thin vertical line indicates the level at the end of the previous fiscal year.
Construction revenue was recognized as a result of progress on projects including a chemical plant for semiconductor materials in South Korea, a fertilizer plant in Nigeria, an electrolyte manufacturing plant for lithium-ion batteries in Japan, and several geothermal power plants in Indonesia, resulting in lower revenue and higher profit year on year.
No applicable matters
| Item | Details |
|---|---|
| Fiscal Period Classification | First quarter |
| Accounting standards | Japanese GAAP |
| Consolidated / non-consolidated | Consolidated |
| Period Covered | 1 April 2026 to 30 June 2026 |
| Net Sales | ¥48,108 million (YoY -2.5%) |
| Operating profit | ¥1,917 million (YoY +186.5%) |
| Ordinary income | ¥3,372 million (YoY +177.8%) |
| Profit attributable to owners of the parent | ¥2,878 million (YoY +414.6%) |
| Net income per share | ¥49.12 |
| Equity ratio | End of the current fiscal period 18.9 / End of previous period 16.7 |
| Total assets | ¥246,466 million |
| Net assets | ¥46,785 million |
| Full-year earnings forecast | Net Sales ¥190,000 million (YoY +3.9%) / Operating profit ¥3,000 million / Ordinary income ¥7,500 million / Profit attributable to owners of the parent ¥6,000 million |
| Annual Dividend Forecast | 0 yen and sen → 25 yen and sen |
| Regional sales | Overseas expansion Construction revenue recognized during the period ¥36,722 million / Domestic Construction revenue recognized during the period ¥11,385 million |
| Orders received and order backlog | Consolidated orders received ¥17,202 million (YoY -31.3%) / Total orders received ¥190 million / Total order backlog ¥4,440 million / Consolidated construction contracts carried forward ¥237,353 million |
| Depreciation and amortization | ¥743 million |
| Disclosure regarding the going concern assumption | No applicable matters |
| Change in accounting policy | Changes due to revisions to standards No / Other changes No / Change in accounting estimate No / Restatement No |
| Changes in the scope of consolidation | New Number of companies 0 / Company name Not disclosed / Excluded Number of companies 0 / Company name Not disclosed |
| Availability of Supplementary Financial Results Materials | Yes |
| Availability of Financial Results Briefing | Whether applicable Yes / Subject person For analysts |
| Issued Shares at Period-End | 58,828,807 |
| Treasury Shares at Period-End | 231,378 |
| Factors Behind Changes in Business Performance | Construction revenue was recognized as a result of progress on projects including a chemical plant for semiconductor materials in South Korea, a fertilizer plant in Nigeria, an electrolyte manufacturing plant for lithium-ion batteries in Japan, and several geothermal power plants in Indonesia, resulting in lower revenue and higher profit year on year. |
Items this document does not state (13)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.Construction revenue was attributed to progress on projects including a chemical plant for semiconductor materials in South Korea, a fertilizer plant in Nigeria, an electrolyte manufacturing plant for lithium-ion batteries in Japan, and several geothermal power plants in Indonesia. No specific factor for the increase in profit, other than the year-on-year figure, was provided.