Okada Aiyon (6294) · InitiativeAchieved
Production Capacity Expansion Plan for the Saitama Plant
First written in FY2017. 1 of 2 entries say "Achieved", first in FY2018-Q3. Latest entry: FY2018-Q3.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Expansion of Construction Equipment Manufacturing Facilities at the Saitama PlantA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2018-Q3AchievedAnnual report
「The following major new facilities, which were still in the planning stage at the end of the previous consolidated fiscal year, were completed during the cumulative third-quarter consolidated accounting period.」
The planned production-capacity expansion equipment for construction machinery at the Saitama plant was completed in December 2017. The investment amounted to ¥220.781 million. - FY2017First statedAnnual report
「㈱アイヨンテック, Saitama Plant (Asaka, Saitama), Japan, construction machinery manufacturing equipment, ¥195 million, —, internal funds, June 2017, December 2017, for the purpose of expanding production capacity.」
The plan calls for work to begin in June 2017 and be completed in December of the same year, with a planned investment of ¥195 million, to expand manufacturing equipment at the Saitama plant.