Facility development, including an exhibition hall, at the Kochi head office
First written in FY2017-Q3. 1 of 4 entries say "Restated". Latest entry: FY2019-Q2.
No other company in this theme has enough history to compare yet.
- FY2019-Q2AdvancedAnnual report
「During the six-month period ended 30 September, we constructed a new office building at the Kochi head office using our proprietary seismic isolation technology, known as “confined ground seismic isolation.”」
Specific progress has been made in the development of the Kochi head office facilities through the construction of a new office building using confined ground seismic isolation. - FY2018SoftenedAnnual report
「Head office (Kochi, Kochi Prefecture); construction machinery business; office; 316; 74; internal funds and borrowings; November 2016; February 2019」
Although the development of facilities at the Kochi head office is progressing, the scheduled completion has been pushed back from August 2018 to February 2019. - FY2017RestatedAnnual report
「Head office (Kochi, Kochi Prefecture); construction machinery business; exhibition hall, offices and other facilities; planned investment: ¥1,919 million; start date: November 2016; scheduled completion: August 2018」
The plan to develop the exhibition hall, offices and other facilities at the Kochi head office continues to be stated, with completion scheduled for August 2018. - FY2017-Q3First statedAnnual report
「Of the maximum estimated net proceeds of ¥3,539.613 million from the public offering and the related third-party allotment, ¥1,145.000 million is scheduled to be allocated by the end of August 2018 to research and development of the press-in machine product group, ¥1,435.000 million by the end of August 2018 to part of the funds for increasing production of machinery for rental in the construction machinery business, and the balance by the end of August 2018 to part of the funds for developing the exhibition hall and other facilities at the Kochi head office.」
A new plan has been presented to allocate the balance of the proceeds from the capital increase to part of the funds for developing the exhibition hall and other facilities at the Kochi head office by the end of August 2018.