Gyropress piling method adopted for the first time in the UK, attracting attention as a new option for addressing flooding challenges that have hindered urban redevelopment

GIKEN LTD.'s Gyropress Method™ was adopted for the first time in the UK and used in flood prevention works in Derby. The GIKEN Group rented out press-in machines, sold related materials and dispatched technical instructors.

Worth reading
69In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
76
¥100 million (total project value: approximately £35 million)
Wording
Conditional
How definitive the wording is.

Announced details

Gyropress Method™ (steel-pipe pile press-in method)GTOSS™ EUROPE comprehensive support service for press-in machine usersGyro Piler™ F401-G1200Silent Piler™ F301-700
Applicable field (uses covered by this announcement)

Flood prevention in the UK, river retaining walls, enhancement of disaster prevention functions, urban regeneration, and construction in confined spaces and on hard ground

What the company reported numerically
Usage history

Press-in technology has been adopted in more than 40 countries and regions (cumulative total and date not stated in the text)

Relationship between the counterparty and the company
GIKEN LTD.6289
Relationship with the Company

Ivor King (C.E.C.) Ltd. is a member of GTOSS™ EUROPE. Giken Europe B.V. rented press-in machine products to the company, sold related materials and dispatched technical instructors. Derby City Council is the project owner, and John Sisk & Son Ltd. is the general contractor.

CounterpartyIvor King (C.E.C.) Ltd.Derby City CouncilJohn Sisk & Son Ltd.

Ivor King (C.E.C.) Ltd. is a contractor that belongs to GTOSS™ EUROPE. Derby City Council is the project owner, and John Sisk & Son Ltd. is the general contractor. Other information on location, representative, capital and year established is Not disclosed.

Location (as indicated in this announcement)

Reach 6, River Derwent Reach, Derby (construction site)

93 steel pipe piles (1,000 mm in diameter and 16 m long) and 192 U-shaped sheet piles (600 mm wide and 9 m long)
Contract Value

Public funding of approximately £35 million (approximately ¥7.6 billion) for the total project. The amount of the individual contract is Not disclosed.

The company does not address Offering price / Impact on Business Performance.

Source (materials cited by the company)

The UK government's investment policy of June 2025 (the detailed document title and institutional information are not provided in the text). Construction illustration and data provided by John Sisk & Son Ltd.

Announced details
ItemDetails
Names of Products / Services CoveredGyropress Method™ (steel-pipe pile press-in method), GTOSS™ EUROPE comprehensive support service for press-in machine users, Gyro Piler™ F401-G1200, Silent Piler™ F301-700
CounterpartyIvor King (C.E.C.) Ltd., Derby City Council, John Sisk & Son Ltd.
Counterparty overviewIvor King (C.E.C.) Ltd. is a contractor that belongs to GTOSS™ EUROPE. Derby City Council is the project owner, and John Sisk & Son Ltd. is the general contractor. Other information on location, representative, capital and year established is Not disclosed.
Relationship with the CompanyIvor King (C.E.C.) Ltd. is a member of GTOSS™ EUROPE. Giken Europe B.V. rented press-in machine products to the company, sold related materials and dispatched technical instructors. Derby City Council is the project owner, and John Sisk & Son Ltd. is the general contractor.
Contract ValuePublic funding of approximately £35 million (approximately ¥7.6 billion) for the total project. The amount of the individual contract is Not disclosed.
Applicable areaFlood prevention in the UK, river retaining walls, enhancement of disaster prevention functions, urban regeneration, and construction in confined spaces and on hard ground
LocationReach 6, River Derwent Reach, Derby (construction site)
Location scale93 steel pipe piles (1,000 mm in diameter and 16 m long) and 192 U-shaped sheet piles (600 mm wide and 9 m long)
Usage historyPress-in technology has been adopted in more than 40 countries and regions (cumulative total and date not stated in the text)
SourceThe UK government's investment policy of June 2025 (the detailed document title and institutional information are not provided in the text). Construction illustration and data provided by John Sisk & Son Ltd.
Items this document does not state (9)
Offering priceContract DateLaunch dateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsImpact on Business PerformanceCounterparty's listed code

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The project required both constructability and environmental considerations at a confined worksite between a river and existing structures, on hard ground and under conditions requiring water-quality protection. The method was valued for its low vibration, low noise, limited spoil generation and space-efficient construction.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Gyropress piling method adopted for the first time in the UK, attracting attention as a new option for addressing flooding challenges that have hindered urban redevelopment | GIKEN LTD. (6289) timely disclosure | Komori