FPSO Baobab Ivoirien safely resumes production following life extension and refurbishment work

FPSO Baobab Ivoirien resumed production on 4 June 2026 after completing life extension and refurbishment work in Dubai, followed by reconnection and commissioning offshore Côte d’Ivoire. MODEC oversaw the refurbishment work and is currently scheduled to continue providing operations and maintenance services through December 2026.

Worth reading
67In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
6700000
More than working hours (zero lost-time injuries)
Wording
Definitive
How definitive the wording is.

Announced details

FPSO Baobab IvoirienO&M (operations and maintenance) services
Applicable field (uses covered by this announcement)

Offshore oil production at the Baobab oilfield offshore Côte d’Ivoire

Launch date4 June 2026 (production resumed; actual date)
What the company reported numerically
Quantitative Effects

More than 6.7 million total working hours completed with zero lost-time injuries (LTIs)

Relationship between the counterparty and the company
MODEC,INC.6269
Relationship with the Company

MODEC oversaw the execution of the refurbishment work and handed the FPSO over to CNR. MODEC is currently continuing to provide O&M services, scheduled through December 2026. In February 2025, MODEC sold ownership of the FPSO to CNR and terminated the charter agreement.

CounterpartyCNR International (Cote d’Ivoire) S.A.R.L.
Location (as indicated in this announcement)

Dubai (refurbishment work); the Baobab oilfield, approximately 65 km southwest offshore from Abidjan, Côte d’Ivoire (operating location)

In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.

Announced details
ItemDetails
Names of Products / Services CoveredFPSO Baobab Ivoirien, O&M (operations and maintenance) services
CounterpartyCNR International (Cote d’Ivoire) S.A.R.L.
Relationship with the CompanyMODEC oversaw the execution of the refurbishment work and handed the FPSO over to CNR. MODEC is currently continuing to provide O&M services, scheduled through December 2026. In February 2025, MODEC sold ownership of the FPSO to CNR and terminated the charter agreement.
Launch date4 June 2026 (production resumed; actual date)
Applicable areaOffshore oil production at the Baobab oilfield offshore Côte d’Ivoire
LocationDubai (refurbishment work); the Baobab oilfield, approximately 65 km southwest offshore from Abidjan, Côte d’Ivoire (operating location)
Quantitative EffectsMore than 6.7 million total working hours completed with zero lost-time injuries (LTIs)
Items this document does not state (11)
Counterparty overviewContract ValueOffering priceContract DateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateLocation scaleUsage historyImpact on Business PerformanceSource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Comprehensive refurbishment work was carried out to extend the service life and improve long-term operability.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
FPSO Baobab Ivoirien safely resumes production following life extension and refurbishment work | MODEC,INC. (6269) timely disclosure | Komori