Risk of Flooding at the Head Office Factory and Operational Suspension from Damage to Both Sites
First written in FY2021. 1 of 2 entries say "Mitigated", first in FY2023. Latest entry: FY2023.
2entries
3years
0from disclosures
How it moved
Same theme, other companies
Risk of site operating disruptions and product supply stoppages due to natural disasters, accidents and other eventsA theme 479 companies write about · 492 as a headwind · 6 as a tailwind
The whole theme swung hardest in 2018: 32 of 132 companies on the "Worse" side.
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 187 companies compared. The sentences above are computed from all 187.Comparing 200 of the theme's 498 threads.Full recordFilings, disclosures and news, newest first
- FY2023MitigatedAnnual report
「本社工場につきましては、自治体より隣接する河川の大規模な氾濫により3m未満の浸水が予想されている地域にあります。そのため、生産工場や屋外キュービクルなど水防対策に取り組むほか、操業停止による影響を最小限に抑えるため、BCP(事業継続計画)も考慮した木津川工場(京都府木津川市)を第二の拠点として稼働させ、リスクの低減を図っております。」
本社工場の最大3m未満の浸水リスクに対し、水防対策に加え、木津川工場を第二拠点として稼働させるBCP対応を実施している。 - FY2021First statedAnnual report
「本社工場につきましては、自治体より隣接する河川の大規模な氾濫により最大3m未満の浸水が予想されている地域にあります。そのため、生産工場や屋外キュービクルなど適宜水防対策に取り組むほか、操業停止による影響を最小限に抑えるため、BCP(事業継続計画)も目的とした木津川工場(京都府木津川市)を第二の拠点としてリスクの低減を図っております。」
本社工場について河川氾濫による最大3m未満の浸水想定を初めて記載し、水防対策と木津川工場を第二拠点とするBCP対応を示している。