Nagaoka International (6239) · InitiativeAchieved
Expansion of the Dalian Factory Building and Production Facilities
First written in FY2018. 1 of 2 entries say "Achieved", first in FY2019-Q1. Latest entry: FY2019-Q1.
2entries
1years
0from disclosures
How it moved
Same theme, other companies
Expansion of the Dalian Factory Building and Production FacilitiesA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2019-Q1AchievedAnnual report
「Based on the plan at the end of the previous consolidated fiscal year, the following major facilities were completed. ... 那賀日造設備(大連)有限公司 China Dalian Water-related and energy-related Plant building, production facilities and other assets September 2018」
The company states that the planned expansion of the Dalian subsidiary's plant building, production facilities and other assets was completed in September 2018. - FY2018First statedAnnual report
「那賀日造設備(大連)有限公司 China Dalian Plant building, production facilities and other assets 205,417 71,737 Internal funds and borrowings December 2017 September 2018」
For its Dalian subsidiary, the company disclosed a plan to expand the plant building, production facilities and other assets at a total cost of ¥205.417 million, of which ¥71.737 million had already been paid, with completion scheduled for September 2018.