Risk of Estimating Total Construction Costs under the Percentage-of-Completion Method

First written in FY2021. 2 of 5 entries say "Restated". Latest entry: FY2026.

5entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2021 – FY2023WorsenedFY20242021: 120212022: 120222023: 120232024: 120242025: 020252026: 12026
Same theme, other companies
Uncertainty in Cost and Progress Estimates for Construction Revenue RecognitionA theme 94 companies write about · 93 as a headwind · 1 as a tailwind

The whole theme swung hardest in 2024: 9 of 64 companies on the "Worse" side.

10 other companies' latest entry also says "Mitigated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 94 companies compared. The sentences above are computed from all 94.
Full recordFilings, disclosures and news, newest first
  1. FY2026MitigatedAnnual report

    「Revenue from performance obligations satisfied over time was ¥5,812.811 million. Changes in the estimate of total construction costs may affect the calculation of the progress percentage and revenue in the next consolidated fiscal year.」

    Revenue subject to the percentage-of-completion method decreased from ¥6,849.597 million in the previous fiscal year to ¥5,812.811 million, reducing the scale of revenue exposed to the impact of estimate changes. However, estimation risk itself remains.
  2. FY2024WorsenedAnnual report

    「Revenue related to performance obligations satisfied over time amounted to ¥7,410.636 million, and changes in estimates of total construction costs may affect the progress rate and revenue in the following consolidated fiscal year.」

    Revenue subject to the percentage-of-completion method increased from ¥5,993 million in the previous fiscal year to ¥7,410.636 million, expanding the scale of potential earnings impact related to estimates of total construction costs.
  3. FY2023RestatedAnnual report

    「Amounts recognized in the consolidated financial statements for the current consolidated fiscal year」

    Revenue related to performance obligations satisfied over time amounted to ¥5,993 million, and the accounting estimation risk that changes in estimates of total construction costs may affect the progress rate and revenue in the following consolidated fiscal year continues to be disclosed.
  4. FY2022RestatedAnnual report

    「Amounts recognized in the consolidated financial statements for the current consolidated fiscal year」

    For construction contracts, revenue of ¥4,945.452 million related to performance obligations satisfied over time was recognized, and the possibility that estimates of total construction costs may affect the progress rate and revenue in the following fiscal year continues to be disclosed.
  5. FY2021First statedAnnual report

    「If total construction costs fluctuate due to unanticipated costs arising from additional work, changes in construction specifications or other factors, this may affect the calculation of the progress rate and revenue from completed construction contracts in the following consolidated fiscal year.」

    For revenue of ¥4,528.560 million recognized under the percentage-of-completion method, the risk that total construction costs may fluctuate due to changes in subcontracting costs, raw material prices, labor hours, site conditions and other factors, affecting the progress rate and revenue in the following fiscal year, was disclosed independently for the first time as a material accounting estimate.
Moved together

"Political, Social and Payment Collection Risks Associated with Overseas Operations" moved the same way as this thread, in the same document, in 2 of its 5 moves.

2★1
  1. ★This thread
  2. 1Political, Social and Payment Collection Risks Associated with Overseas Operations2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Nagaoka International yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Risk of Estimating Total Construction Costs under the Percentage-of-Completion Method | NAGAOKA INTERNATIONAL CORPORATION (6239) | Komori