Large order received by a subsidiary
矢澤フェロマイト株式会社 (a subsidiary of NAGAOKA INTERNATIONAL CORPORATION)
Renewal work for the concentrator tanks and other facilities at Kashiwara Water Purification Plant
The order value is approximately ¥400 million, including tax. The amount of the impact on earnings itself is Not disclosed.
Fiscal year ending June 2027 (revenue has been incorporated for the portion of the work expected to progress during the fiscal year)
The consolidated earnings forecast for the fiscal year ending June 2027 incorporates revenue for the portion of the work expected to progress during the fiscal year.
The contractual delivery date is March 2028. Revenue for the portion of the work expected to progress during the fiscal year has been incorporated into the consolidated earnings forecast for the fiscal year ending June 2027.
| Item | Details |
|---|---|
| Event name | Large order received by a subsidiary |
| Subject Entity | 矢澤フェロマイト株式会社 (a subsidiary of NAGAOKA INTERNATIONAL CORPORATION) |
| Target Locations / Products | Renewal work for the concentrator tanks and other facilities at Kashiwara Water Purification Plant |
| Amount of Impact on Business Performance | The order value is approximately ¥400 million, including tax. The amount of the impact on earnings itself is Not disclosed. |
| Accounting period in which recognized | Fiscal year ending June 2027 (revenue has been incorporated for the portion of the work expected to progress during the fiscal year) |
| Impact on Earnings Forecast | The consolidated earnings forecast for the fiscal year ending June 2027 incorporates revenue for the portion of the work expected to progress during the fiscal year. |
| Outlook | The contractual delivery date is March 2028. Revenue for the portion of the work expected to progress during the fiscal year has been incorporated into the consolidated earnings forecast for the fiscal year ending June 2027. |
Items this document does not state (18)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.A formal contract was entered into for the project for which the company had been named the prospective winning bidder following the tender conducted on 29 July 2026.