Notice Regarding a Large Order Received by a Subsidiary
矢澤フェロマイト株式会社 (consolidated subsidiary of the filing company)
Improvement work for the sodium hydroxide injection facilities and related equipment at the Misato Water Purification Plant
The company formally executed the contract on 26 March 2026 for the project for which it had been designated the prospective successful bidder following the bid opening held on 18 March 2026.
Fiscal year ending June 2026. The company plans to apply a method of recognizing revenue based on the progress of the construction work.
The company plans to apply a method of recognizing revenue based on the progress of the construction work. The contractual delivery deadline is October 2029. The impact on results for the fiscal year ending June 2026 is immaterial.
| Item | Details |
|---|---|
| Event name | Notice Regarding a Large Order Received by a Subsidiary |
| Date of occurrence | 26 March 2026 (date the formal contract was executed) |
| Subject Entity | 矢澤フェロマイト株式会社 (consolidated subsidiary of the filing company) |
| Target Locations / Products | Improvement work for the sodium hydroxide injection facilities and related equipment at the Misato Water Purification Plant |
| Cause | The company formally executed the contract on 26 March 2026 for the project for which it had been designated the prospective successful bidder following the bid opening held on 18 March 2026. |
| Accounting period in which recognized | Fiscal year ending June 2026. The company plans to apply a method of recognizing revenue based on the progress of the construction work. |
| Outlook | The company plans to apply a method of recognizing revenue based on the progress of the construction work. The contractual delivery deadline is October 2029. The impact on results for the fiscal year ending June 2026 is immaterial. |
Items this document does not state (18)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The company formally executed the contract on 26 March 2026 for the project for which it had been designated the prospective successful bidder at the bid opening on 18 March 2026.