Solar Energy Business and Company-Owned Utility-Scale Solar Power Plants

First written in FY2018. 9 of 24 entries say "Restated". Latest entry: 2026-08-07.

24entries
9years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2024-Q2 – 2026-08-072018: 12019: 420192020: 420202021: 320212022: 420222023: 320232024: 320242025: 120252026: 12026
Same theme, other companies
Commencing Electricity Sales from Solar Power Plants and Monetizing the BusinessA theme 26 companies write about · 1 as a headwind · 25 as a tailwind

Klass moved to the "Worse" side of this theme in 2021, 5 years before the typical company in this theme (2026).

The whole theme swung hardest in 2024: 3 of 16 companies on the "Worse" side.

9 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 26 companies compared. The sentences above are computed from all 26.
Full recordFilings, disclosures and news, newest first
  1. 2026-08-07RestatedEarnings

    「The Solar and Energy business and the electricity sales business, including the Mikazuki Sunshine Park megasolar power plant in Sayo, Hyogo Prefecture, progressed steadily.」

    The steady progress of the Solar and Energy business and electricity sales business, including the company’s own megasolar power plant, was reconfirmed.
  2. FY2025-H1RestatedAnnual report

    「The solar energy business and the power-sales business, including the MIKAZUKI SUNSHINE PARK mega-solar power plant in Sayo, Hyogo Prefecture, progressed smoothly.」

    The solar energy business and the power-sales business, including our mega-solar facilities, progressed smoothly during the current interim consolidated accounting period.
  3. FY2024Restrictions on power sales due to output curtailmentAnnual report

    「Meanwhile, the power-sales business, including the MIKAZUKI SUNSHINE PARK mega-solar power plant in Sayo, Hyogo Prefecture, operated smoothly, but on some days we had no choice but to comply with Kansai Electric Power's requests for output curtailment, preventing us from selling all of the electricity generated.」

    While our mega-solar facilities operated smoothly, there were instances in which we could not sell all of the electricity generated because of a power company's requests for output curtailment.
  4. FY2024-Q2RestatedAnnual report

    「Development of medium-sized and larger projects continued to be sluggish in the solar energy business. Meanwhile, the power-sales business, including the MIKAZUKI SUNSHINE PARK mega-solar power plant in Sayo, Hyogo Prefecture, operated smoothly.」

    While development of medium-sized and larger projects remained sluggish, the power-sales business, including our mega-solar facilities, continued to operate smoothly.
  5. FY2024-Q1WorsenedAnnual report

    「Development of medium-sized and larger projects was sluggish in the solar energy business. Meanwhile, the power-sales business, including the MIKAZUKI SUNSHINE PARK mega-solar power plant in Sayo, Hyogo Prefecture, operated smoothly.」

    While the power-sales business at our mega-solar facilities operated smoothly, development of medium-sized and larger projects related to the corporate business was sluggish.
  6. FY2023AdvancedAnnual report

    「In the solar energy business segment, we will focus on selling solar power generation systems for companies, where demand is growing in response to the SDGs, as well as storage batteries and other related equipment, while developing new products such as V2H in collaboration with automobile dealers.」

    In addition to conventional solar and storage battery sales, the company announced the development of V2H, a new product, in collaboration with automobile dealers. Development of the corporate market remains insufficient, and revenue from the solar energy business was ¥97 million.
  7. FY2023-Q2RestatedAnnual report

    「Although development of the corporate market, which we expect to expand from the perspective of promoting the SDGs, remains insufficient, construction starts for medium-sized projects increased in the solar energy business.」

    While development of the corporate market remains insufficient, construction starts for medium-sized projects increased.
  8. FY2023-Q1AdvancedAnnual report

    「Although development of the corporate market, which we expect to expand from the perspective of promoting the SDGs, remains insufficient, the solar energy business performed well as construction starts increased for medium-sized projects. The mega-solar power generation business continued to operate smoothly.」

    While development of the corporate market remains insufficient, construction starts for medium-sized projects increased, and the solar energy business performed well. Our mega-solar facilities also continued to operate.
  9. FY2022ReframedAnnual report

    「In the solar energy business segment, we will promote initiatives for businesses aimed at decarbonisation in response to the SDGs.」

    The direction of the solar energy business was repositioned from its previous focus on power-sales projects to corporate business aimed at addressing the SDGs and decarbonisation.
  10. FY2022-Q3WorsenedAnnual report

    「In the solar energy business, low-voltage solar projects for power sales declined sharply following regulatory revisions. In addition, installation work on projects already ordered was delayed by delays in equipment deliveries, resulting in sluggish performance.」

    In addition to the sharp decline in low-voltage solar projects, installation work was delayed by delays in equipment deliveries, and the business has remained sluggish.
  11. FY2022-Q2Sharp decline in low-voltage projects; seeking new marketsAnnual report

    「In the solar energy business, performance remained sluggish as low-voltage solar projects for power sales declined sharply following regulatory revisions, while we explored new markets, including those related to the SDGs. Meanwhile, the mega-solar power generation business continued to operate smoothly.」

    Low-voltage solar projects for power sales were described as having declined sharply rather than merely declined, and the company was exploring new markets, including those related to the SDGs, although the business remained sluggish. Its own mega-solar facilities continued to operate.
  12. FY2022-Q1RestatedAnnual report

    「In the solar energy business, although we expect the corporate market to expand from the perspective of promoting the SDGs, the business remained sluggish as low-voltage solar projects for power sales declined, while the mega-solar power generation business continued to operate smoothly.」

    While we expect the corporate market to expand, low-voltage solar projects for power sales remained sluggish, while our mega-solar facilities continued to operate smoothly.
  13. FY2021-Q3WorsenedAnnual report

    「Although the corporate market is expected to expand going forward, the solar energy business remained weak as conventional low-voltage solar projects intended for power sales declined.」

    Although the corporate market is expected to expand, conventional low-voltage solar projects intended for power sales declined, and the solar energy business remained weak.
  14. FY2021-Q2WorsenedAnnual report

    「The solar energy business remained weak due to delays in receiving orders and starting construction, while the large-scale solar power generation business continued to operate smoothly.」

    In addition to some construction projects carried over from the previous quarter, delays in receiving orders and starting construction caused the solar energy business to remain weak. Meanwhile, our large-scale solar power plant continued to operate.
  15. FY2021-Q1Some construction projects carried overAnnual report

    「In the solar energy business, some projects were carried over to the second quarter or later because construction starts were delayed, but the large-scale solar power generation business has been operating smoothly.」

    Construction starts for some solar projects were delayed, resulting in projects being carried over to the second quarter or later, while our large-scale solar power plant continued to operate smoothly.
  16. FY2020AdvancedAnnual report

    「Although electricity purchase prices continued to decline, we steadily secured orders for small-scale industrial solar projects using idle real estate, and sales amounted to ¥351 million, up 2.7% year on year.」

    Amid continued declines in purchase prices, orders for small-scale industrial solar projects progressed, resulting in a 2.7% year-on-year increase in sales in the solar energy business.
  17. FY2020-Q3RestatedAnnual report

    「In the solar energy business, construction progressed as scheduled, enabling sales to be recorded.」

    In the solar energy business, construction progressed as scheduled, leading to the recording of sales.
  18. FY2020-Q2AdvancedAnnual report

    「In the solar energy business, construction progressed as scheduled, including projects carried over from the first quarter, enabling us to increase sales.」

    Construction in the solar energy business progressed as scheduled, including projects carried over from the first quarter, and sales increased.
  19. FY2020-Q1RestatedAnnual report

    「The large-scale solar power generation business has been operating smoothly.」

    Our large-scale solar power plant has continued to operate.
  20. FY2019AdvancedAnnual report

    「Amid a difficult environment for securing orders for large-scale solar power generation system projects due to continued reductions in electricity purchase prices, we focused on proposing small-scale industrial solar installations using idle real estate and selling peripheral equipment such as storage batteries and IH systems. As a result, we were able to halt the decline in sales, which amounted to ¥342 million, up 9.3% year on year.」

    In response to the worsening environment under the feed-in tariff scheme, we expanded into small-scale projects, storage batteries and IH systems, restoring sales in the solar energy business to 9.3% above the previous fiscal year. Power sales from our own large-scale solar plant also progressed smoothly.
  21. FY2019-Q3AdvancedAnnual report

    「Progress on the long-delayed permits and approvals for equipment installation enabled sales to progress. The large-scale solar power generation business has been operating smoothly.」

    Progress on permits and approvals advanced sales in the solar business, while our large-scale solar power plant continued to operate.
  22. FY2019-Q2RestatedAnnual report

    「The large-scale solar power generation business has been operating smoothly.」

    The continued operation of our large-scale solar power plant has been confirmed.
  23. FY2019-Q1RestatedAnnual report

    「The large-scale solar power generation business has been operating smoothly.」

    The continued operation of our large-scale solar power plant has been confirmed.
  24. FY2018First statedAnnual report

    「We installed the large-scale solar power plant “Mikazuki Sunshine Park,” with output of approximately 1 megawatt, on land we own in Sayo, Sayo District, Hyogo Prefecture, and operate a power sales business.」

    We operate a business selling and installing solar power generation systems as well as our own power sales business.
Moved together

"Expansion of Addressable Markets Through the Use of Core Technologies" moved the same way as this thread, in the same document, in 4 of its 24 moves.

443333★123456
  1. ★This thread
  2. 1Expansion of Addressable Markets Through the Use of Core Technologies4×
  3. 2Expanding the Business Scope through Specialty-Function Tatami Mats, Renovations and Content4×
  4. 3Expansion of orders in the secondary battery manufacturing equipment business3×
  5. 4Developing New Markets by Strengthening Marketing Functions3×
  6. 5Development of One-of-a-Kind Products for IoT and Robotics Technologies3×
  7. 6Quarterly earnings fluctuations caused by delays in revenue recognition for orders received3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Klass yet. It last moved in the Earnings of 2026-08-07: "Restated".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Solar Energy Business and Company-Owned Utility-Scale Solar Power Plants | KLASS Corporation (6233) | Komori