Construction of a testing and research building
First written in FY2024-Q3. 6 of 9 entries say "Advanced", first in FY2024. Latest entry: 2026-11-13.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「As another initiative, we opened the Yao Technology Research Center, which will serve as a hub for future new product development and technological research, strengthening our overall technological foundation and promoting new product development. At the Kawai Plant, we are also constructing a technology research institute, aiming to begin operations around October 2026, and will promote the development of more attractive products by coordinating the activities of both research facilities.」
The Yao Technology Research Center has opened, while construction of the technology research institute at the Kawai Plant is progressing, with operations targeted to begin around October 2026. The company's research and development infrastructure has progressed to the opening and construction stages. - FY2026-H1ReframedAnnual report
「To accelerate further refinement of products focused on temperature and humidity control and products with a low environmental impact, the company is currently constructing a technology research center.」
The research and development infrastructure previously described as research and testing buildings is now referred to as a technology research center, and construction is underway as a development hub for temperature- and humidity-controlled products and products with a low environmental impact. - FY2025-H1AdvancedAnnual report
「In addition, to further accelerate the development of energy-saving products toward carbon neutrality by 2050, we are proceeding in parallel with the construction of testing and research buildings at both manufacturing plants.」
The construction of research and testing buildings at the Yao Plant and Kawai Plant has progressed from the planning and resolution stage to the construction stage, with work proceeding in parallel at both plants. - FY2024AdvancedAnnual report
「As previously disclosed, we plan cumulative capital investment of ¥8,413.000 million by the fiscal year ending March 2026 for the complete rebuilding of the Yao Plant and the construction of research and testing buildings at the Yao Plant and Kawai Plant. At a meeting of the Board of Directors held on 12 April 2024, the company resolved to acquire fixed assets, specifically the construction of the Second Research and Testing Building, as set out below, and plans to enter into a contract in October 2024. Acquisition cost: approximately ¥600.000 million (total for the building, equipment, etc.) Handover date: March 2026 (scheduled)」
The company has specified its capital investment plan, including the construction of research and testing buildings at the Yao Plant and Kawai Plant, and resolved to acquire the Second Research and Testing Building at the Kawai Plant for approximately ¥600 million, with handover scheduled for March 2026. - FY2024-Q3First statedAnnual report
「In addition, we resolved to construct a research and testing building.」
The company describes for the first time its resolution to construct a research and testing building as a new capital investment project to develop its research and development infrastructure.