Strengthening the operating infrastructure through a core systems upgrade

First written in FY2022. 1 of 5 entries say "Restated". Latest entry: FY2026.

5entries
5years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2022 – FY20252022: 120222023: 120232024: 120242025: 120252026: 12026
Same theme, other companies
Investment in Upgrading Core Business SystemsA theme 159 companies write about · 5 as a headwind · 154 as a tailwind

81 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 159 companies compared. The sentences above are computed from all 159.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「Head office (Higashinari-ku, Osaka City) Core systems upgrade ¥450 million ¥184.25 million Internal funds During FY2023 During FY2027」

    The Company disclosed that ¥184.25 million of the planned ¥450 million investment in the core systems upgrade had already been paid, indicating that the plan had moved into the investment execution phase. The scheduled completion remains during FY2027.
  2. FY2025Higher investment and delayed completionAnnual report

    「Head office (Higashinari-ku, Osaka City) Core systems upgrade ¥450 million - Internal funds During FY2023 During FY2027」

    For the core systems upgrade plan, the planned investment was increased from ¥400 million to ¥450 million, and the scheduled completion date changed from during FY2026 to during FY2027.
  3. FY2024Higher investment and delayed completionAnnual report

    「Head office (Higashinari-ku, Osaka City) Core systems upgrade ¥400 million - Internal funds During FY2023 During FY2026」

    For the core systems upgrade plan, the planned investment was increased from the ¥300 million previously disclosed to ¥400 million, and the scheduled completion date changed from during FY2024 to during FY2026.
  4. FY2023RestatedAnnual report

    「Head office (Higashinari-ku, Osaka City) Core systems upgrade ¥300 million Internal funds During FY2023 During FY2024」

    The Company continues its plan to invest ¥300 million from internal funds in the core systems upgrade, to be implemented from FY2023 through FY2024.
  5. FY2022First statedAnnual report

    「Head office (Higashinari-ku, Osaka City) Core systems upgrade ¥300 million Internal funds During FY2023 During FY2024」

    For the core systems upgrade, the Company has disclosed for the first time an investment plan to spend ¥300 million from internal funds, to be implemented from FY2023 through FY2024.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Sanei's next results are scheduled for 2026-10-26. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.