Plans to expand the Toyama Plant considered
First written in FY2017. 6 of 12 entries say "Advanced", first in FY2022-Q1. Latest entry: FY2027-H1.
No other company in this theme has enough history to compare yet.
- FY2027-H1RestatedAnnual report
「At the Toyama Kureha plant, built as a new production base, some processes of the manufacturing division have been transferred, and we are pursuing further rationalization and efficiency improvements in production. However, manufacturing expenses, including depreciation and other costs associated with constructing the plant, have increased.」
The transfer of processes to the Toyama Kureha Plant and production streamlining and efficiency improvements are continuing. Increased manufacturing expenses related to the new plant are also stated. - FY2026AdvancedAnnual report
「At the Toyama Kureha Plant, which was built as a new production base, part of the manufacturing process has been transferred, and further streamlining and efficiency improvements in production are under way.」
The Toyama Plant expansion plan progressed from the land acquisition and construction-cost recognition stage to the completion of the new plant and the transfer of part of the manufacturing process. - 2026-06-04AchievedGeneral Meeting of Shareholders
「2025年5月に竣工いたしました富山呉羽工場が2026年度より本格的な稼働となります。」
新工場は建設・工程移行段階から竣工し、本格稼働段階へ移った。 - FY2026-H1AdvancedAnnual report
「At the Toyama Kureha Plant, which was built as a new production base, part of the manufacturing process has been transferred, and further streamlining and efficiency improvements in production are under way.」
The Toyama Kureha Plant progressed from the construction planning and construction-cost recognition stage to the stage of transferring part of the manufacturing process and advancing production streamlining and efficiency improvements. - FY2025AdvancedAnnual report
「The current-period increase in construction in progress mainly includes ¥268.964 million in construction costs for the new Toyama Kureha Plant.」
Construction of the Toyama Kureha Plant made tangible progress through an increase of ¥268.964 million in construction in progress during the period. The planned completion date under the facilities plan is December 2025. - FY2024AdvancedAnnual report
「The current-period increase in construction in progress mainly includes ¥185.546 million in construction costs for the new Toyama Kureha Plant.」
Construction of the new Toyama Kureha Plant has made tangible progress through the recognition of ¥185.546 million in construction in progress. - FY2023AdvancedAnnual report
「At a meeting of the Board of Directors held on 18 April 2023, a resolution was passed to acquire fixed assets (construction of a new plant), and at a meeting of the Board of Directors held on 9 May 2023, a resolution was passed on the acquisition cost of the fixed assets.」
A resolution was passed to construct a new plant on 7,991.47 m² of land in Toyama, Toyama Prefecture, at an investment of approximately ¥1.2 billion, in response to the aging and limited space of the Toyama Plant. Construction was scheduled to begin in March 2024 and operations were scheduled to start in December 2025, with the aims of transferring part of the manufacturing process, streamlining and improving production efficiency, and creating a high-quality, safe workplace. - FY2022-Q2Increase in land balanceAnnual report
「Land 226,722 432,902」
Land on the balance sheet increased from ¥226.722 million at the end of the previous fiscal year to ¥432.902 million at the end of the second quarter accounting period. Although this report does not specify the relationship with the previously disclosed acquisition of land for plant construction, an increase in the land balance related to the plant expansion can be confirmed. - FY2022-Q1AdvancedAnnual report
「The land is being acquired as a site for a plant to further increase production capacity. (2) Area: 7,991.47 m² (3) Acquisition cost: ¥206.179 million (4) Contract date: 30 June 2021 (5) Property handover date: 29 July 2021」
A contract was signed for land in Toyama, Toyama Prefecture, on which to build a plant to further increase production capacity. The land covers 7,991.47 m² and was acquired for ¥206.179 million, with handover scheduled for 29 July 2021. The Toyama Plant expansion plan progressed to the specific land acquisition stage. - FY2019ReframedAnnual report
「To improve productivity at the Toyama plant, we recognize addressing the aging of the facilities as an issue. To ensure stable production in the future, we will consider measures to eliminate inefficiencies and work toward creating a better plant environment.」
The wording has changed from considering plant expansion on the assumption of increased orders for steel towers to considering measures focused on improving productivity, addressing aging facilities and eliminating inefficiencies. - FY2018RestatedAnnual report
「We expect orders for steel towers to continue increasing and intend to consider measures to expand the plant.」
The policy of considering measures to expand the Toyama Plant in anticipation of increased orders for steel towers has been reiterated. - FY2017First statedAnnual report
「We expect orders for steel towers to continue increasing and intend to consider measures to expand the plant.」
In response to the aging, limited space and inefficient layout of the Toyama Plant, a policy of considering expansion measures was indicated in anticipation of increased orders for steel towers.