Komori
Revision of earnings forecasts5921Kawagishi Bridge Works Co.,Ltd.Construction and Materials

Notice Regarding Revisions to Earnings Forecasts for the Second Quarter (Interim Period) of the Fiscal Year Ending September 2026

The standalone earnings forecasts for the second quarter (interim period) of the fiscal year ending September 2026 have been revised. Net sales have been increased by 16.4% following the recognition of revenue upon completion of a large-scale construction project, while operating profit, ordinary profit and interim net income have been reduced slightly. The full-year forecasts remain unchanged.

Worth reading
55In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
16.4
%
Wording
Avoiding a definitive answer
How definitive the wording is.

Revised forecast

Fiscal year ending September 2026 · Second quarter (interim period)Previous forecast published 14 November 2025
Net Sales11,000→12,799million
+16.4%
Operating profit500→487million
-2.6%
Ordinary income600→584million
-2.6%
Profit attributable to owners of the parent420→401million
-4.3%
Net income per share152.76→146.21yen and sen
-4.3%

The bar length represents the relative magnitude of change, based on the item that changed the most in this document. The percentage change shown by the dotted line is calculated from the two reported figures because the company did not provide the rate.

Reason for the revision

Net sales are expected to exceed the previous forecast following recognition of revenue from the completion of a large-scale construction project. Profit at each stage is expected to be broadly in line with the previous forecast.

Previous-period resultsNet Sales ¥11,764 million (interim net income per share: yen and sen) / Operating profit ¥958 million (interim net income per share: yen and sen) / Ordinary income ¥1,089 million (interim net income per share: yen and sen) / Interim net income ¥721 million (interim net income per share: yen and sen) / Interim net income per share ¥254.68 million (interim net income per share: yen and sen)
Consolidated / non-consolidatedNon-consolidated
Revised forecast
ItemDetails
Net Sales¥11,000 million → ¥12,799 million(+16.4%)
Operating profit¥500 million → ¥487 million(-2.6%)
Ordinary income¥600 million → ¥584 million(-2.6%)
Profit attributable to owners of the parent¥420 million → ¥401 million(-4.3%)
Net income per share152.76 yen and sen → 146.21 yen and sen
Fiscal Period CoveredFiscal year ending September 2026
Period CoveredSecond quarter (interim period)
Publication date of previous forecast14 November 2025
Previous-period resultsNet Sales ¥11,764 million (interim net income per share: yen and sen) / Operating profit ¥958 million (interim net income per share: yen and sen) / Ordinary income ¥1,089 million (interim net income per share: yen and sen) / Interim net income ¥721 million (interim net income per share: yen and sen) / Interim net income per share ¥254.68 million (interim net income per share: yen and sen)
Reason for the revisionNet sales are expected to exceed the previous forecast following recognition of revenue from the completion of a large-scale construction project. Profit at each stage is expected to be broadly in line with the previous forecast.
Consolidated / non-consolidatedNon-consolidated
Items this document does not state (2)
Details and amount of extraordinary lossDividend forecast revision

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Net sales for the interim period are expected to exceed the previous forecast because revenue from the completion of a large-scale construction project will be recognized. Profit at each stage is expected to remain broadly at the same level as in the previous forecast. The full-year earnings forecasts remain unchanged.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding Revisions to Earnings Forecasts for the Second Quarter (Interim Period) of the Fiscal Year Ending September 2026 | Kawagishi Bridge Works Co.,Ltd. (5921) timely disclosure | Komori