Sumitomo Metal Mining (5713) · InitiativeAdvanced
Commercial Operation of the Scandium Recovery Business
First written in FY2016. 1 of 2 entries say "Advanced", first in FY2017. Latest entry: FY2017.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Equipment Development for Commercial Operation of the Scandium Recovery BusinessA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2017AdvancedAnnual report
「タガニートHPALニッケル社 タガニート工場他 フィリピン北スリガオ州 製錬 スカンジウム回収事業 4,000 267 平成28年6月 平成30年3月」
スカンジウム回収事業について、予算40億円、既支出額2億67百万円、平成30年3月完工予定の設備計画として進行している。 - FY2016First statedAnnual report
「We developed technology to recover scandium from the HPAL process and, following scale-up testing at a pilot plant, decided to construct a commercial-scale operating plant.」
The capital investment plan specifies construction beginning in June 2016, completion in March 2018 and a budget of ¥4 billion.