Envipro Holdings (5698) · RiskDropped
Permitting and Protracted-Approval Risks in Solar Power Plant Development
First written in FY2017. 1 of 2 entries say "Dropped", first in FY2022. Latest entry: FY2022.
2entries
6years
0from disclosures
How it moved
Same theme, other companies
Risk of Delays in Development Permits and Approvals, Environmental Assessments, and Consensus-Building with Local StakeholdersA theme 8 companies write about · 9 as a headwind · 0 as a tailwind
0 other companies' latest entry also says "Dropped".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2022DroppedAnnual report
「All shares of 株式会社E3 were transferred.」
Following the transfer of all shares of E3, which had operated the solar power business, the risk of permitting delays in solar power plant development no longer appears in the current fiscal year's risk disclosures. - FY2017First statedAnnual report
「The Group's results of operations may be affected if the period required to reach power plant construction becomes longer than expected or if circumstances arise that force it to abandon the project midway.」
The company identifies as separate risks the permits required under the Forest Act, environmental laws and other legislation as solar power plants become larger, complex application procedures, prolonged construction periods and the possibility of abandoning projects.