Land acquisition and capital investment as BCP measures
First written in FY2018. 9 of 12 entries say "Advanced", first in FY2019. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026Capital investment continues, but the investment amount has declinedAnnual report
「The main capital investments during the fiscal year were made primarily in molding and firing equipment, with the aim of expanding and rationalizing the production system and renewing existing equipment. The total investment was ¥622.126 million.」
The company invested ¥622.126 million, primarily in molding and firing equipment. Although the scale declined from ¥827.691 million in the previous fiscal year, the company continued to expand and rationalize the production system and renew existing equipment. - 2026-05-27AdvancedGeneral Meetings of Shareholders
「Capital investment, including intangible fixed assets, during the current fiscal year was ¥626,011 thousand. Major investments included molding and firing equipment to expand and rationalize production capacity and renew existing equipment.」
The disclosure reports investments to expand and rationalize production capacity and renew existing equipment. - FY2025AdvancedAnnual report
「The main capital investments during the fiscal year were made primarily in molding and firing equipment, with the aim of expanding and rationalizing the production system and renewing existing equipment. In addition, the ceramics business invested ¥827.691 million, mainly in seismic reinforcement work on buildings at the Higashiyama plant and the renewal of air-conditioning equipment with higher energy efficiency as part of efforts to reduce GHG emissions.」
The ceramics business invested ¥827.691 million in molding and firing equipment, seismic reinforcement, and the renewal of air-conditioning systems with higher energy efficiency. - FY2025-H1AdvancedAnnual report
「Property, plant and equipment decreased 1.5% from the end of the previous fiscal year to ¥6,998.249 million. Tangible fixed assets increased 2.6% from the end of the previous fiscal year to ¥4,785.517 million, mainly due to capital investment.」
During the interim accounting period, the company advanced capital investment, and tangible fixed assets increased 2.6% from the end of the previous fiscal year to ¥4,785.517 million. - FY2024AdvancedAnnual report
「The main capital investments during the fiscal year were made at the Sakai and Higashiyama plants, primarily in molding, firing, and grinding equipment, with the aim of expanding and rationalizing the production system and renewing existing equipment. The company also invested ¥645.452 million mainly in environmental improvements, including seismic reinforcement work on the building at the Sakai plant and renewal of the air-conditioning system in the main building at the Higashiyama plant.」
In addition to molding, firing, and grinding equipment at both plants, the company carried out seismic reinforcement work and renewed air-conditioning systems, investing ¥645.452 million in the ceramics business. - FY2023SoftenedAnnual report
「During the fiscal year, the company continued to make capital investments aimed at strengthening production equipment and enhancing and reinforcing its research and development functions. …Capital investment during the fiscal year, including leased assets and intangible fixed assets, amounted to ¥316.420 million, and」
Capital investment continued, but the total for the fiscal year was ¥316.420 million, including ¥303.514 million for the ceramics business. The company stated that the scale had declined from ¥936.563 million in the previous fiscal year and that it had not made any large-scale capital investments or renewals. - FY2021AdvancedAnnual report
「The main capital investments during the fiscal year were made at the Sakai and Higashiyama plants, primarily in new production buildings, molding equipment, and firing equipment, with the aim of expanding and rationalizing the production system and renewing existing equipment. The total investment was ¥936.563 million.」
The company installed new production buildings, molding equipment, and firing equipment at the Sakai and Higashiyama plants, investing ¥936.563 million. Investments to expand and rationalize the production system and renew existing equipment have moved into the execution phase. - FY2021-Q3AdvancedAnnual report
「Fixed assets increased 5.1% to ¥7,232.420 million, mainly due to a 6.0% increase in tangible fixed assets to ¥5,334.195 million. These increases were attributable to the acquisition of facilities upon completion of the new building at the Higashiyama Plant.」
Completion of the new building at the Higashiyama plant and acquisition of equipment have progressed, and investment to expand the production system and renew existing equipment has moved into the execution phase. - FY2020AdvancedAnnual report
「The main capital investments during the fiscal year were made at the Sakai and Higashiyama plants, primarily in molding and firing equipment, with the aim of expanding and rationalizing the production system and renewing existing equipment. The total investment was ¥1,946.808 million.」
The company advanced investments related to BCP measures, expansion and rationalization of the production system, and renewal of existing equipment, investing ¥1,946.808 million at the Sakai and Higashiyama plants. This included the down payment for construction of a new building at the Higashiyama plant, indicating increased progress in capital investment. - FY2020-Q2AdvancedAnnual report
「Property, plant and equipment increased 7.7% from the end of the previous fiscal year to ¥6,402.687 million. Machinery and equipment rose 13.2% to ¥1,504.245 million, while construction in progress increased substantially from the end of the previous fiscal year to ¥358.283 million. These increases mainly reflected the renewal of production equipment and down payments, among other items, for the new building at the Higashiyama plant.」
Progress was made on renewing production equipment and paying the down payment for the new building at the Higashiyama plant. Machinery and equipment amounted to ¥1,504.245 million and construction in progress to ¥358.283 million. This indicates progress on the rationalization and renewal of existing equipment and investment related to the new building. - FY2019AdvancedAnnual report
「The main capital investments during the fiscal year consisted primarily of the acquisition of land for BCP purposes and the rationalization and renewal of existing production equipment at the Sakai and Higashiyama plants, totaling ¥866.668 million.」
The company acquired land as a BCP measure and rationalized and renewed production equipment at the Sakai and Higashiyama plants, bringing investment in the ceramics business to ¥866.668 million. - FY2018First statedAnnual report
「The main capital investments during the fiscal year consisted primarily of the acquisition of land for BCP purposes and the rationalization and renewal of existing production equipment at the Sakai and Higashiyama plants, totaling ¥701.583 million.」
The company reported for the first time that it acquired land as a BCP measure and rationalized and renewed production equipment at the Sakai and Higashiyama plants, investing ¥701.583 million.