Maruwa (5344) · RiskMaterialised
Extensions to Lighting Project Timelines Due to Labor Shortages and Impact on Performance
First written in FY2018-Q3. 1 of 1 entries say "Materialised", first in FY2018-Q3. Latest entry: FY2018-Q3.
1entries
1years
0from disclosures
How it moved
Same theme, other companies
Construction delays caused by labor shortages in the construction industryA theme 35 companies write about · 35 as a headwind · 0 as a tailwind
Maruwa moved to the "Worse" side of this theme in 2018, 2 years before the typical company in this theme (2020).
The whole theme swung hardest in 2022: 6 of 14 companies on the "Worse" side.
8 other companies' latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 35 companies compared. The sentences above are computed from all 35.