Asahi Concrete Works (5268) · RiskDropped
Deterioration in Public-Works Progress Due to Adverse Weather
First written in FY2017-Q2. 3 of 6 entries say "Dropped", first in FY2017. Latest entry: FY2020.
6entries
5years
0from disclosures
How it moved
Same theme, other companies
Delayed revenue recognition due to delays in starting constructionA theme 48 companies write about · 52 as a headwind · 0 as a tailwind
The whole theme swung hardest in 2026: 11 of 24 companies on the "Worse" side.
6 other companies' latest entry also says "Dropped".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 48 companies compared. The sentences above are computed from all 48.Full recordFilings, disclosures and news, newest first
- FY2020DroppedAnnual report
「(1)公共事業への売上依存度が大きいことについて (2)主要原材料の購入価格の騰貴について (3)債権管理について (4)新型コロナウイルス感染症拡大について」
当年度の事業等のリスクとして列挙された項目に、天候不順による公共事業進捗悪化は含まれていない。 - FY2019-Q2MaterialisedAnnual report
「当社の関連するコンクリート製品業界では、豪雨、台風等の天候不順や人手不足等も影響して公共工事の進捗が遅れ気味となるなど、厳しい事業環境が続きました。」
豪雨・台風等の天候不順が人手不足とともに公共工事の進捗遅延に影響したと記載され、天候リスクが実際の事業環境に現れている。 - FY2018DroppedAnnual report
「(1)公共事業への売上依存度が大きいことについて (2)主要原材料の購入価格の騰貴について (3)債権管理について」
当年度の事業等のリスク欄では、従来記載されていた天候不順による公共事業進捗悪化は独立したリスクとして記載されていない。 - FY2018-Q3MaterialisedAnnual report
「当社関連のコンクリート製品業界では、人手不足や天候不順などから得意先の工事工程が安定せず納品遅れが生じており、また受注競争は依然厳しいものがあります。」
天候不順が人手不足とともに得意先の工事工程を不安定にし、納品遅れが実際に生じていると記載している。 - FY2017DroppedAnnual report
「(1)公共事業への売上依存度が大きいことについて (2)主要原材料の購入価格の騰貴について (3)債権管理について」
前四半期に記載された天候不順による公共事業進捗悪化は、当年度の「事業等のリスク」欄では独立したリスクとして記載されていない。 - FY2017-Q2First statedAnnual report
「Progress was sluggish because of labor shortages and adverse weather, and the business environment remained challenging.」
Adverse weather is identified separately from the existing labor-shortage risk as a factor impairing progress on public works.