- 2026-06-26AdvancedManagement Planning
「Infrastructure-strengthening investment: approximately ¥1.05 billion」
The allocation of business growth investment, including payment-system infrastructure strengthening and improvement and new development for information processing, was made more concrete. - FY2026AdvancedAnnual report
「Total capital expenditures made during the consolidated fiscal year were ¥2,851.217 million, consisting mainly of ¥636.628 million for network and hardware construction and ¥2,214.589 million for software investments.」
Capital investment in the payment and information processing platforms continued, with ¥2,851.217 million invested during the current fiscal year. Plans scheduled for completion in March 2027, including payment system expansion, construction of the information processing platform, and hardening of the payment system, also remain in place. - FY2026-H1AdvancedAnnual report
「Funds used in investing activities totaled ¥2,078.791 million, mainly consisting of ¥311.215 million in expenditures for the acquisition of property, plant and equipment, ¥941.107 million for the acquisition of intangible assets, ¥224.491 million for the acquisition of shares in a subsidiary, and ¥500 million in long-term loans.」
During the interim period, the company also invested in property, plant and equipment of ¥311.215 million and intangible assets of ¥941.107 million, among other investments. - FY2025AdvancedAnnual report
「Total capital expenditures made during the consolidated fiscal year were ¥2,538.564 million, consisting mainly of ¥529.101 million for network and hardware construction and ¥1,991.731 million for software investments.」
Capital investment in the payment and information processing platforms continued, with ¥2,538.564 million invested during the current fiscal year. Plans scheduled for completion in March 2027, including payment system expansion, the information processing platform, and hardening of the payment system, remain in place. - FY2025-H1AdvancedAnnual report
「Funds used in investing activities totaled ¥1,381.487 million, mainly consisting of ¥229.132 million in expenditures for the acquisition of property, plant and equipment and ¥1,127.024 million in expenditures for the acquisition of intangible assets.」
During the interim period, the company also invested in property, plant and equipment and intangible assets, disclosing total investment expenditures including ¥1,127.024 million for the acquisition of intangible assets. - FY2024AdvancedAnnual report
「Total capital expenditures made during the consolidated fiscal year were ¥4,643.987 million, consisting mainly of ¥1,407.324 million for hardware construction and ¥3,214.564 million for software investments.」
Capital investment in the payment and information processing platforms was carried out, and the total investment and breakdown between hardware and software were disclosed. - FY2023First statedAnnual report
「Data-center scalability and security enhancements」
From March 2025 through March 2027, the company plans to invest ¥574 million to enhance data center scalability and security, ¥1,504 million to expand the payment system, ¥2,334 million to build the information processing platform, and ¥3,632 million to harden the payment system and for related purposes.