Decision and Details
Board of DirectorsAcquisition of Grid-Scale Battery Storage Facilities and Associated Rights, etc. (the Acquisition)
This is because, after comprehensively considering the facility scale, operating conditions and expected profitability, the Company determined that the acquisition would contribute to expanding the Group's revenue base (recurring revenue) and enhancing corporate value over the medium to long term. The acquisition will also promote the effective use of renewable energy and contribute to the realization of a decarbonized, sustainable society.
The impact on the Company's consolidated results for the fiscal year ending January 2027 is expected to be immaterial.
| Item | Details |
|---|---|
| Matter Covered | Acquisition of Grid-Scale Battery Storage Facilities and Associated Rights, etc. (the Acquisition) |
| Decision-Making Body | Board of Directors |
| Decision Date | 30 September 2026 |
| Implementation Date | Scheduled facility delivery date: by 30 April 2027 (予定). The payment date for the amount due at contract signing is 30 September 2026. The balance of the purchase price will be paid within 10 business days of acceptance inspection approval and within 10 business days of confirmation of grid connection and normal operation, respectively. |
| Period Covered | Expected operating period: 20 years |
| Amount | Acquisition price: ¥700 million or more but less than ¥800 million |
| Quantity / scale | Rated output: 1,999 kW; storage capacity: 8,194 kWh; 1 project |
| Impact on Business Performance | The impact on the Company's consolidated results for the fiscal year ending January 2027 is expected to be immaterial. |
| Reason | This is because, after comprehensively considering the facility scale, operating conditions and expected profitability, the Company determined that the acquisition would contribute to expanding the Group's revenue base (recurring revenue) and enhancing corporate value over the medium to long term. The acquisition will also promote the effective use of renewable energy and contribute to the realization of a decarbonized, sustainable society. |
| Future plans | The facilities are scheduled to be delivered by 30 April 2027. If any matters requiring disclosure arise in the future, they will be announced promptly. |
| Remarks | Expected first-year gross sales yield: approximately 33.9%; expected project IRR: approximately 11.3%. Neither figure constitutes a guarantee of future earnings or yields. |
Items this document does not state (2)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.This decision was made after comprehensively considering the facility scale, operating conditions and expected profitability, and determining that the acquisition would contribute to expanding the Group's recurring revenue and enhancing corporate value over the medium to long term. The Company also cited the effective use of renewable energy and its contribution to the realization of a decarbonized, sustainable society.