Announced details
Power grid stabilization and grid operation associated with the proliferation of renewable energy power plants
テス・エンジニアリング株式会社 is a consolidated subsidiary of TESS Holdings Co.,Ltd. The counterparty is a subsidiary of DIGITAL GRID Corporation, and the transaction involves テス・エンジニアリング株式会社 receiving an order for a grid-scale battery storage facility from the counterparty.
Based in Minato-ku, Tokyo. Representative Director: Shimada Takehisa (嶋田剛久). A subsidiary of DIGITAL GRID Corporation. DIGITAL GRID Corporation provides aggregation services for distributed power sources and related services.
Izumo, Shimane Prefecture
In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.
| Item | Details |
|---|---|
| Names of Products / Services Covered | Grid-scale storage facilities |
| Counterparty | デジタルグリッドアセットマネジメント株式会社 |
| Counterparty overview | Based in Minato-ku, Tokyo. Representative Director: Shimada Takehisa (嶋田剛久). A subsidiary of DIGITAL GRID Corporation. DIGITAL GRID Corporation provides aggregation services for distributed power sources and related services. |
| Relationship with the Company | テス・エンジニアリング株式会社 is a consolidated subsidiary of TESS Holdings Co.,Ltd. The counterparty is a subsidiary of DIGITAL GRID Corporation, and the transaction involves テス・エンジニアリング株式会社 receiving an order for a grid-scale battery storage facility from the counterparty. |
| Launch date | July 2026 (scheduled delivery) |
| Applicable area | Power grid stabilization and grid operation associated with the proliferation of renewable energy power plants |
| Location | Izumo, Shimane Prefecture |
| Location scale | PCS output: 2,000 kW; capacity: 8,128 kWh (4 HUAWEI-manufactured units of 2,032 kWh each) |
Items this document does not state (10)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The facility is installed to stabilize the power grid, which is becoming less stable as renewable energy power plants proliferate. The project is being pursued as one of the focus business areas under the Group's medium-term management plan, “TX2030.”