Earth (4985) · InitiativeAchieved
Construction of a New Mondamin Plant and Nearly Doubling Production Capacity
First written in FY2016. 1 of 2 entries say "Achieved", first in FY2017-Q1. Latest entry: FY2017-Q1.
2entries
1years
0from disclosures
How it moved
Same theme, other companies
Ako Plant Mondamin New Factory Construction and Production Capacity DoublingA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2017-Q1AchievedAnnual report
「前連結会計年度末において計画中であった主要な設備の新設のうち、当第1四半期連結累計期間に完成したものは、次のとおりであります。」
計画されていた赤穂工場のモンダミン生産設備が平成29年1月に完成した。帳簿価額の合計は44億71百万円である。 - FY2016First statedAnnual report
「The principal capital investments during the fiscal year consisted of construction of a new Mondamin plant and purchases of production facilities, including land for a plant of ARS CHEMICAL(THAILAND)CO.,LTD., totaling ¥5,408 million.」
Construction of a new Mondamin plant was under way. The investment plan called for total investment of ¥5.2 billion, completion in January 2017 and approximately double the production capacity after completion.