Development of the Fukushima Plant for OLED Materials
First written in FY2016. 6 of 7 entries say "Restated". Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. - FY2025RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. - FY2023RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Note 3 Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. There are no plans to install or dispose of material equipment. - FY2020RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. It states that there are no material plans to install new facilities. - FY2018RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research facility for organic EL materials. - FY2017RestatedAnnual report
「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」
The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. - FY2016First statedAnnual report
「April 2015: The Fukushima Plant was completed for the synthesis and manufacture of organic EL materials.」
The Fukushima Plant was completed in April 2015, and ¥340 million was invested in equipment at the plant during the fiscal year.