Chemipro Kasei (4960) · InitiativeRestated

Development of the Fukushima Plant for OLED Materials

First written in FY2016. 6 of 7 entries say "Restated". Latest entry: FY2026.

7entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY20262016: 120162017: 120172018: 120182019: 020192020: 120202021: 020212022: 020222023: 120232024: 020242025: 120252026: 12026
Same theme, other companies
Development of the Fukushima Plant as a manufacturing and research base for OLED materialsA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials.
  2. FY2025RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials.
  3. FY2023RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Note 3 Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. There are no plans to install or dispose of material equipment.
  4. FY2020RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials. It states that there are no material plans to install new facilities.
  5. FY2018RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research facility for organic EL materials.
  6. FY2017RestatedAnnual report

    「Fukushima Plant (Tamura, Fukushima Prefecture) Chemicals business Organic EL materials manufacturing and research facility」

    The company continues to position the Fukushima Plant as a manufacturing and research center for organic EL materials.
  7. FY2016First statedAnnual report

    「April 2015: The Fukushima Plant was completed for the synthesis and manufacture of organic EL materials.」

    The Fukushima Plant was completed in April 2015, and ¥340 million was invested in equipment at the plant during the fiscal year.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Chemipro Kasei yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Development of the Fukushima Plant for OLED Materials | CHEMIPRO KASEI KAISHA,LTD. (4960) | Komori