Construction of the Second U.S. Plant
First written in FY2020. 3 of 5 entries say "Advanced", first in FY2021. Latest entry: 2026-05-21.
No other company in this theme has enough history to compare yet.
- 2026-05-21AdvancedFinancial Results Presentation
「Strengthen the production system by advancing the second-plant project.」
Continue to advance the second U.S. plant project and strengthen the production system. - FY2023AdvancedAnnual report
「We will advance Phase 2 construction at the second plant in Rancho Cucamonga, California, which began operations last year, to expand production capacity and improve production efficiency in the U.S.」
Following the start of Phase 1 operations at the second plant, the project moved into the stage of advancing Phase 2 construction. - FY2022AchievedAnnual report
「In addition, to establish a new production system in the United States, the Company had been advancing plans to construct a second plant in Rancho Cucamonga, California. Phase 1 construction was completed in June 2022, and the second plant began operations. The plant’s operation will increase production capacity in the United States and improve production efficiency.」
Phase 1 construction of the second U.S. plant was completed and operations began in June 2022. The project has progressed from the construction-planning stage to the operational stage. - FY2021AdvancedAnnual report
「The following are the plans for the construction of significant new facilities and other projects as of the end of the fiscal year. T.HASEGAWA U.S.A.,INC. California, United States Food plant construction Approximately ¥2.7 billion Approximately ¥1.5 billion Internal funds July 2021 February 2022 2,000 tonnes per year」
The construction of the second U.S. plant became a specific plan involving an investment of approximately ¥2.7 billion, approximately ¥1.5 billion already paid, scheduled completion in February 2022, and additional capacity of 2,000 tonnes per year. - FY2020First statedAnnual report
「T.HASEGAWA U.S.A.,INC. California, United States Food plant construction Undetermined 1,098 Internal funds Fiscal year ending September 2021 Fiscal year ending September 2022」
For the second U.S. plant, the plan states that ¥1,098 million has already been paid, the project will be financed with internal funds, construction will begin during the fiscal year ending September 2021 and be completed during the fiscal year ending September 2022. The total investment and additional capacity after completion remain undetermined.