Development of the Internal Core System
First written in FY2019-Q1. 4 of 8 entries say "Advanced", first in FY2019-Q2. Latest entry: FY2026.
The whole theme swung hardest in 2021: 9 of 48 companies on the "Worse" side.
14 other companies' latest entry also says "Achieved".
- FY2026AchievedAnnual report
「The internal core system that was under development at the end of the previous consolidated fiscal year was completed in October 2025 and became fully operational.」
The new internal core system that was under development in the previous fiscal year was completed in October 2025 and became fully operational. - FY2024AdvancedAnnual report
「Filing company Head office (Minato-ku, Tokyo) Internal core system 289,000 — Internal funds April 2024 October 2025」
Following the full operation of the previous internal core system, a capital investment plan was established for a new internal core system, totaling ¥289 million and scheduled for completion in October 2025. - FY2020RestatedAnnual report
「The internal core system that was under development at the end of the previous consolidated fiscal year was completed in October 2019 and became fully operational.」
The completion and full operation of the new internal core system were also confirmed in the annual report. - FY2020-Q3AchievedAnnual report
「The internal core system that was under development at the end of the previous consolidated fiscal year was completed in October 2019 and became fully operational.」
The new internal core system, planned at a total cost of ¥550 million, was completed in October 2019 and became fully operational. - FY2019AdvancedAnnual report
「Internal core system 550,000 233,075 Internal funds March 2018 October 2019」
For development of the internal core system, total planned investment was ¥550 million and the amount already paid was ¥233.075 million. The amount already paid increased from the previous disclosure, and the planned investment was also revised. - FY2019-Q3AdvancedAnnual report
「Head office (Minato-ku, Tokyo) Software development business Embedded software development business Internal core system 530,000 220,184 Internal funds March 2018 October 2019」
For development of the internal core system, the amount already paid increased from ¥135.938 million to ¥220.184 million. Total planned investment was ¥530 million, with completion scheduled for October 2019. - FY2019-Q2AdvancedAnnual report
「Head office (Minato-ku, Tokyo) Software development business Embedded software development business Internal core system Planned investment: 530,000 Amount already paid: 135,938 Funding: Internal funds Start date: March 2018 Scheduled completion: October 2019」
For development of the internal core system, the amount already paid increased from ¥64.882 million to ¥135.938 million, and the scheduled completion date changed from the fiscal year ending March 2020 to October 2019. Total planned investment was ¥530 million. - FY2019-Q1First statedAnnual report
「Head office (Minato-ku, Tokyo) Software development business Embedded software development business Internal core system Planned investment: ¥530.000 million Amount already paid: ¥64.882 million Funding: Internal funds Start date: March 2018 Scheduled completion: Fiscal year ending March 2020」
The company disclosed a capital investment plan totaling ¥530 million for development of an internal core system. Completion was scheduled during the fiscal year ending March 2020.