Construction of new soundproofing-material production equipment at 武漢日特固汽車零部件有限公司
First written in FY2020. 10 of 12 entries say "Restated". Latest entry: FY2026-H1.
No other company in this theme has enough history to compare yet.
- FY2026-H1RestatedAnnual report
「During the current interim consolidated accounting period, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the soundproofing-material production equipment project at 武漢日特固汽車零部件有限公司, or material changes to the plans. - FY2025-H1RestatedAnnual report
「During the current interim consolidated accounting period, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the soundproofing-material production equipment project at 武漢日特固汽車零部件有限公司, or material changes to the plans. This does not indicate that the equipment has been completed. - FY2023RestatedAnnual report
「There are no plans for constructing important facilities or undertaking similar projects during the current consolidated fiscal year.」
No material changes to existing major facility plans or new plans have been disclosed, including the soundproofing-material production equipment at 武漢日特固汽車零部件有限公司. - FY2023-Q2RestatedAnnual report
「During the first six months of the current consolidated fiscal year, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the construction plans. - FY2023-Q1RestatedAnnual report
「During the first quarter of the fiscal year under review, there were no significant changes in major facilities or in plans for major facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the plans. - FY2022-Q2RestatedAnnual report
「During the first six months of the current consolidated fiscal year, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the construction plans. - FY2022-Q1RestatedAnnual report
「During the first quarter of the fiscal year under review, there were no significant changes in major facilities or in plans for major facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the plans. - FY2021AdvancedAnnual report
「武漢日特固汽車零部件有限公司 Main plant (Wuhan, Hubei Province, China) Automotive products-related business Soundproofing-material production equipment 2,270 1,447 Internal funds and borrowings November 2019 April 2021」
The company disclosed that the Wuhan soundproofing-material production equipment project had a total cost of ¥2.27 billion, of which ¥1.447 billion had already been paid, with completion scheduled for April 2021. Completion of the equipment itself has not been explicitly stated. - FY2021-Q3RestatedAnnual report
「During the first nine months of the current consolidated fiscal year, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the construction plans. - FY2021-Q2RestatedAnnual report
「During the first six months of the current consolidated fiscal year, there were no material changes in major facilities or material changes to the plans for constructing important facilities as of the end of the previous consolidated fiscal year.」
The company has reconfirmed that there have been no material changes in major facilities, including the Wuhan soundproofing-material production equipment project, or material changes to the construction plans. - FY2021-Q1RestatedAnnual report
「During the first quarter of the fiscal year under review, there were no significant changes in major facilities or in plans for major facilities as of the end of the previous consolidated fiscal year.」
No material changes to the plans for major facilities, including the Wuhan soundproofing-material production equipment project, have been disclosed. This does not indicate that the project has been completed. - FY2020First statedAnnual report
「武漢日特固汽車零部件有限公司 Main plant (Wuhan, Hubei Province, China) Automotive products-related business Soundproofing-material production equipment 2,240 266 Internal funds and borrowings November 2019 April 2021」
For the new company established by 武漢日特固防音配件有限公司 in September 2019, the company disclosed for the first time an investment plan totaling ¥2.24 billion for soundproofing-material production equipment. Completion was scheduled for April 2021.