Komori
Fuso Pharmaceutical Industries (4538) · InitiativeAchieved

Completion and commencement of operations at the Second Formulation Building of the Ibaraki Plant

First written in FY2016. 6 of 9 entries say "Restated". Latest entry: FY2024.

9entries
9years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY2022AdvancedFY2023 – FY20242016: 220162017: 120172018: 120182019: 120192020: 020202021: 120212022: 120222023: 120232024: 12024
Same theme, other companies
Completion and commencement of operations at the Second Formulation Building of the Ibaraki PlantA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2024AchievedAnnual report

    「The expansion work has now been completed, and operations began on 22 January 2024.」

    The expansion work to add a new line to the powdered dialysis agent production facilities for artificial kidneys at the second formulation building of the Ibaraki Plant was completed, and operations began on 22 January 2024.
  2. FY2023AdvancedAnnual report

    「During the fiscal year, the company raised funds under this policy to invest in adding a new line to the powdered dialysis agent production facilities at the second formulation building of the Ibaraki Plant, as well as for research and development activities.」

    The company invested in adding a new line to the powdered dialysis agent production facilities at the existing second formulation building of the Ibaraki Plant.
  3. FY2022RestatedAnnual report

    「April 2016: Second formulation building established at the Ibaraki Plant (Kitaibaraki, Ibaraki Prefecture)」

    The company reconfirmed in its corporate history that the second formulation building at the Ibaraki Plant had been established.
  4. FY2021RestatedAnnual report

    「April 2016: Second formulation building established at the Ibaraki Plant (Kitaibaraki, Ibaraki Prefecture)」

    The company reconfirmed in its corporate history that the second formulation building at the Ibaraki Plant had been established.
  5. FY2019RestatedAnnual report

    「April 2016: Second formulation building established at the Ibaraki Plant (Kitaibaraki, Ibaraki Prefecture)」

    The company reconfirmed in its corporate history that the second formulation building at the Ibaraki Plant had been established.
  6. FY2018RestatedAnnual report

    「April 2016: Second formulation building established at the Ibaraki Plant (Kitaibaraki, Ibaraki Prefecture)」

    The company reconfirmed in its corporate history that the second formulation building at the Ibaraki Plant had been established.
  7. FY2017RestatedAnnual report

    「The second formulation building at the Ibaraki Plant, a production facility for powdered dialysis agents, was completed and began operations in April 2016, further strengthening the company’s ability to ensure a stable supply of Kindaly dialysis agents, including in the event of a disaster.」

    The company reconfirmed the completion and commencement of operations of the second formulation building in April 2016 and the strengthening of its stable supply system.
  8. FY2017-Q1RestatedAnnual report

    「In production, the completion and commencement of operations in April 2016 of the second formulation building added at the Ibaraki Plant strengthened the company’s ability to ensure a more stable supply of Kindaly dialysis agents for artificial kidneys, including in the event of a disaster.」

    The company reconfirmed the completion and commencement of operations of the second formulation building at the Ibaraki Plant in April 2016 and the strengthening of its stable supply system.
  9. FY2016First statedAnnual report

    「The company had been carrying out construction of a second formulation building at the Ibaraki Plant as a production facility for powdered dialysis agents. With the building completed and becoming operational in April 2016, the company strengthened its ability to ensure a more stable supply of Kindaly dialysis agents, including in the event of a disaster.」

    The company reported the specific facility milestone of completing and commencing operations of the powdered dialysis agent production facility in April 2016.
Moved together

"Increased Investment in Pharmaceutical Manufacturing Equipment at the Joto Plant" moved the same way as this thread, in the same document, in 2 of its 9 moves.

22★12
  1. ★This thread
  2. 1Increased Investment in Pharmaceutical Manufacturing Equipment at the Joto Plant2×
  3. 2Response to the Generic Drug Market and Sales Promotion2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Fuso Pharmaceutical Industries yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Completion and commencement of operations at the Second Formulation Building of the Ibaraki Plant | Fuso Pharmaceutical Industries,Ltd. (4538) | Komori