Notice of the Execution of a Design and Construction Contract for the Okayama No. 2 Plant

A design and construction contract was executed with 千代田エクスワンエンジニアリング株式会社 to construct a new plant on the site of the Okayama Plant. The plan is to increase production capacity for powdered dialysis agents and reorganize and consolidate the domestic production facilities by transferring the functions of the Daito Plant.

Worth reading
61In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
140
¥100 million (total investment)
Wording
Conditional
How definitive the wording is.

Decision and Details

Board of Directors

Execution of a design and construction contract for Okayama No. 2 Plant

Decision30 September 2026
ImplementationContract executed on 30 September 2026 (completed); construction scheduled to start in December 2026; completion scheduled for March 2028; manufacturing scheduled to begin in December 2028
Going forwardConstruction scheduled to start in December 2026, completion scheduled for March 2028, and manufacturing scheduled to begin in December 2028
AmountTotal investment: approximately ¥14 billion (including buildings, production equipment and related costs)
Quantity / scaleBuilding area: approximately 3,400 m²; total floor area: approximately 8,800 m²; five-story steel-frame structure; automated high-bay warehouse to be included
Reason

Further strengthening of the BCP (business continuity plan) and improvement of production efficiency, expansion of the supply capacity for powdered dialysis agents, reorganization and consolidation of the domestic production facility network, and improvement of manufacturing efficiency

Impact on Business Performance

There is no change to the earnings forecast for the fiscal year ending March 2027

Decision and Details
ItemDetails
Matter CoveredExecution of a design and construction contract for Okayama No. 2 Plant
Decision-Making BodyBoard of Directors
Decision Date30 September 2026
Implementation DateContract executed on 30 September 2026 (completed); construction scheduled to start in December 2026; completion scheduled for March 2028; manufacturing scheduled to begin in December 2028
AmountTotal investment: approximately ¥14 billion (including buildings, production equipment and related costs)
Quantity / scaleBuilding area: approximately 3,400 m²; total floor area: approximately 8,800 m²; five-story steel-frame structure; automated high-bay warehouse to be included
Impact on Business PerformanceThere is no change to the earnings forecast for the fiscal year ending March 2027
ReasonFurther strengthening of the BCP (business continuity plan) and improvement of production efficiency, expansion of the supply capacity for powdered dialysis agents, reorganization and consolidation of the domestic production facility network, and improvement of manufacturing efficiency
Related previous disclosuresMedium-Term Management Policy "FUSO Vision 2030 Next Stage," announced on 8 August 2025; "Summary of Financial Results for the Fiscal Year Ended March 2026 [Japanese GAAP] (Non-consolidated)," announced on 12 May 2026
Future plansConstruction scheduled to start in December 2026, completion scheduled for March 2028, and manufacturing scheduled to begin in December 2028
Items this document does not state (2)
Period CoveredGoverning Rule

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The objectives are to strengthen the BCP (business continuity plan), improve production efficiency, expand the supply capacity for powdered dialysis agents, reorganize and consolidate the domestic production facility network, and improve manufacturing efficiency.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice of the Execution of a Design and Construction Contract for the Okayama No. 2 Plant | Fuso Pharmaceutical Industries,Ltd. (4538) timely disclosure | Komori