Rebuilding of the Kansai Branch office building and rental buildings
First written in FY2020-Q2. 2 of 5 entries say "Restated". Latest entry: FY2022-Q1.
No other company in this theme has enough history to compare yet.
- FY2022-Q1AchievedAnnual report
「Kansai Branch (Chuo-ku, Osaka, Osaka Prefecture) Pharmaceuticals Real estate business Redevelopment Branch office building, rental buildings, etc. April 2021」
The redevelopment of the Kansai Branch office building and rental buildings, etc. was completed in April 2021, the previously scheduled completion date, which is listed as the completion date for major facilities. - FY2021RestatedAnnual report
「Kansai Branch (Chuo-ku, Osaka, Osaka Prefecture) Pharmaceutical business Real estate business Rebuilding Branch office building and rental buildings, etc. 1,571 484 Internal funds November 2019 April 2021」
The rebuilding plan for the Kansai Branch office building and rental buildings, etc. continued at a total cost of ¥1,571 million, with ¥484 million already paid and completion scheduled for April 2021. - FY2021-Q2SoftenedAnnual report
「Kansai Branch (Chuo-ku, Osaka, Osaka Prefecture) Pharmaceutical business Real estate business Rebuilding Branch office building and rental buildings, etc. 1,571 483 Internal funds November 2019 April 2021」
For the rebuilding plan for the Kansai Branch office building and rental buildings, etc., the planned total investment increased from ¥1,551 million to ¥1,571 million, and the amount already paid was ¥483 million. The scheduled completion date changed from February 2021 to April 2021, postponing completion of the plan. - FY2020-Q3RestatedAnnual report
「Kansai Branch (Chuo-ku, Osaka, Osaka Prefecture) Pharmaceutical business Real estate business Rebuilding Branch office building and rental buildings, etc. 1,551 30 Internal funds November 2019 February 2021」
The rebuilding plan for the Kansai Branch office building and rental buildings, etc. continued to be disclosed. The total cost was ¥1,551 million, with ¥30 million already paid, work beginning in November 2019 and completion scheduled for February 2021. There was no material change to the plan. - FY2020-Q2First statedAnnual report
「Kansai Branch (Chuo-ku, Osaka, Osaka Prefecture) Pharmaceutical business Real estate business Rebuilding Branch office building and rental buildings, etc. 1,551 2 Internal funds November 2019 February 2021」
The rebuilding plan for the Kansai Branch office building and rental buildings, etc. was finalised at a total cost of ¥1,551 million, with ¥2 million already paid and funded from internal funds. Work began in November 2019 and was scheduled for completion in February 2021.