Construction and full-scale operation of the new topical formulation building at the Shizuoka facility
First written in FY2017-Q1. 1 of 3 entries say "Softened", first in FY2017-Q2. Latest entry: FY2017-Q3.
No other company in this theme has enough history to compare yet.
- FY2017-Q3AchievedAnnual report
「Shizuoka facility (Fujieda, Shizuoka Prefecture) Pharmaceuticals Production equipment October 2016」
The completion date for the production equipment at the Shizuoka facility was stated as October 2016, reaching the full-scale operation date scheduled in the previous filing. - FY2017-Q2SoftenedAnnual report
「However, the project was not complete because some production equipment and other facilities were still being tested. Full-scale operation, which had been scheduled for September 2016, was changed to October 2016.」
The new topical formulation building had been completed, but testing of some equipment was continuing, and the scheduled start of full-scale operation was postponed from September to October 2016. - FY2017-Q1First statedAnnual report
「The new topical formulation building at the Shizuoka facility (Fujieda, Shizuoka Prefecture) was completed in May 2016. However, the project was not complete because some production equipment and other facilities were still being tested. Full-scale operation was scheduled to begin in September 2016.」
The building was completed, but testing of some equipment was continuing, and full-scale operation was scheduled for September 2016.