How it moved
ProgressHeldSoftenedWorseFirst statedFY2018AdvancedFY2019RestatedFY2021AdvancedFY2022 – FY2025-H12018: 120182019: 120192020: 020202021: 120212022: 120222023: 120232024: 120242025: 12025
Same theme, other companies
Expansion and rationalization of pharmaceutical production and R&D facilitiesA theme 4 companies write about · 0 as a headwind · 4 as a tailwind

Kaken Pharmaceutical moved to the "Worse" side of this theme in 2025.

1 other company's latest entry also says "Softened".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026-H1SoftenedAnnual report

    「Shizuoka Facility (Fujieda, Shizuoka Prefecture) Pharmaceuticals Replacement Pharmaceutical production equipment April 2025 However, the plan has not been completed because some production equipment and other facilities are still being tested. Full-scale operations are scheduled to begin in fiscal 2025.」

    The replacement of pharmaceutical production equipment at the Shizuoka Facility was stated to have an April 2025 completion date, but the plan remains incomplete because some equipment is still being tested, with full-scale operations scheduled to begin in fiscal 2025.
  2. FY2025-H1AdvancedAnnual report

    「Shizuoka Facility (Fujieda, Shizuoka Prefecture) Pharmaceuticals Replacement Pharmaceutical production equipment 3,240 1,053 Internal funds January 2024 January 2025 Expansion of production capacity」

    For the replacement plan for pharmaceutical production equipment at the Shizuoka Facility, total planned investment was ¥3,240 million and ¥1,053 million had already been paid. Completion in January 2025 and the objective of expanding production capacity continue to be indicated.
  3. FY2023-Q3AdvancedAnnual report

    「Shizuoka Facility (Fujieda, Shizuoka Prefecture) Pharmaceuticals Replacement Production equipment 2,845 2 Internal funds January 2024 January 2025 Expansion of production capacity」

    A replacement plan for the production equipment at the Shizuoka Facility was newly finalised, with planned investment of ¥2,845 million, work scheduled to begin in January 2024 and be completed in January 2025, and the objective of expanding production capacity.
  4. FY2022AdvancedAnnual report

    「The main capital investment during the fiscal year totalled ¥3,003 million, focused on the installation and renewal of manufacturing equipment at the Shizuoka Plant.」

    The installation and renewal of manufacturing equipment at the Shizuoka Plant continued, with ¥3,003 million invested in the pharmaceutical business. This was an increase from ¥1,862 million in the previous fiscal year.
  5. FY2021RestatedAnnual report

    「The main capital investment during the fiscal year totalled ¥1,862 million, focused on the installation and renewal of manufacturing equipment at the Shizuoka Plant.」

    The installation and renewal of manufacturing equipment at the Shizuoka Plant continued, with ¥1,862 million invested in the pharmaceutical business.
  6. FY2019AdvancedAnnual report

    「The main capital investment during the fiscal year totalled ¥2,286 million, focused on the installation and renewal of manufacturing equipment and construction of a quality control building at the Shizuoka Plant.」

    Capital investment, including the installation and renewal of manufacturing equipment at the Shizuoka Plant, continued. The quality control building was completed in October 2018. Capital investment in the pharmaceutical business totalled ¥2,286 million.
  7. FY2018First statedAnnual report

    「The main capital investment during the fiscal year totalled ¥1,874 million, focused on the installation and renewal of manufacturing equipment and construction of a quality control building at the Shizuoka Plant.」

    The installation and renewal of manufacturing equipment and construction of a quality control building at the Shizuoka Plant were specifically reported for the first time as ¥1,874 million of capital investment during the year.
Moved together

"Continuation of R&D investment" moved the same way as this thread, in the same document, in 4 of its 7 moves.

444222★123456
  1. ★This thread
  2. 1Continuation of R&D investment4×
  3. 2Recording of overseas revenue4×
  4. 3Implementation of Shareholder Returns4×
  5. 4Pharmaceutical licensing in Japan and overseas2×
  6. 5Strengthening the New Drug Pipeline and Accelerating Research and Development2×
  7. 6Credit, foreign exchange, market and liquidity risks, and customer concentration2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Kaken Pharmaceutical's next results are scheduled for 2026-11-09. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.