Installation of New Manufacturing Equipment for New Urethane Bead Products
First written in FY2018-Q1. 3 of 4 entries say "Advanced", first in FY2018-Q2. Latest entry: FY2018.
No other company in this theme has enough history to compare yet.
- FY2018AdvancedAnnual report
「Machinery and equipment Nagoya Plant Urethane bead manufacturing equipment ¥1.541 billion Kyoto Plant Urethane bead manufacturing equipment ¥373 million」
The company has recorded equipment additions of ¥1.541 billion at the Nagoya Plant and ¥373 million at the Kyoto Plant for urethane bead manufacturing equipment. - FY2018-Q3AdvancedAnnual report
「Filing company Nagoya Plant Other 1 plant Tokai, Aichi Other Urethane bead manufacturing equipment (for new products) Petroleum and transportation-related industries 2,030 146 Internal funds April 2017 March 2018 4,620」
For urethane bead manufacturing equipment for new products, the amount already paid increased from ¥85 million to ¥146 million, indicating progress in executing the plan. - FY2018-Q2AdvancedAnnual report
「Filing company Nagoya Plant Other 1 plant Tokai, Aichi Other Urethane bead manufacturing equipment (for new products) Petroleum and transportation-related industries 2,030 85 Internal funds April 2017 March 2018 4,620」
For urethane bead manufacturing equipment for new products, the amount already paid increased from ¥6 million to ¥85 million, indicating progress in executing the plan. Total planned investment is ¥2.03 billion, with completion scheduled for March 2018 and a resulting capacity increase of 4,620 tonnes per year. - FY2018-Q1First statedAnnual report
「Filing company Nagoya Plant Other 1 plant Tokai, Aichi Other Urethane bead manufacturing equipment (for new products) Petroleum and transportation-related industries 2,030 6 Internal funds April 2017 March 2018 4,620」
The company has confirmed plans to newly install urethane bead manufacturing equipment for new products at the Nagoya Plant and one other plant. Total planned investment is ¥2.03 billion, with work starting in April 2017 and completion scheduled for March 2018. The resulting capacity increase is expected to be 4,620 tonnes per year.